Senior Project Control, Strukton Construction WLL, UAD Road Improvement Project

START Date: 
December, 2018

Developed detailed programme, allocate budget and resources, monitor, reporting and submit claims with substanstiation.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Senior Project Control, Strukton Construction WLL, UAD Road Improvement Project

START Date: 
December, 2018

Developed detailed programme, allocate budget and resources, monitor, reporting and submit claims with substanstiation.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Civil Engineer/ Scheduler, Poyry Energy, Incorporated (Philippines), Power Plants

START Date: 
June, 2016
END Date: 
May, 2018

Responsibilities:

Experience Hours (Planning & Scheduling): 
3850
Experience Hours (Cost Management): 
3850
Experience Hours (Forensic Analysis): 
3850

Senior Planning (Scheduler) Engineer, Consolidated Contractor Company (Jordan), Remaining Works of Saraya Aqaba Project (Jordan)

START Date: 
November, 2015
END Date: 
May, 2016

Responsibilities:

Experience Hours (Planning & Scheduling): 
1150
Experience Hours (Cost Management): 
1150
Experience Hours (Forensic Analysis): 
1150

Senior Planning (Scheduler) Engineer, Consolidated Contractors Company (Oman), Development Of Muscat international Airport (MC1)

START Date: 
January, 2010
END Date: 
November, 2015

Responsibilities:

Experience Hours (Planning & Scheduling): 
11500
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
11500

Planning (Scheduler) Engineer, BF Corporation, Robinson's Place

START Date: 
March, 1995
END Date: 
November, 1995

Responsibilities:

  • Prepared Baseline Schedule, Histogram and S-Curves.
  • Prepared Progress Reports and Cost Reports.
  • Evaluated sub-contractors’ and suppliers’ billings.
  • Prepare correspondence and construction methodology.

Project Involved:

  • Robinson’s Place (Philippines)
Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
1600

Cost and Field Engineer, Newco Builder and Development Corporation, Various Hospitals and roads constructions

START Date: 
January, 1998
END Date: 
May, 2001

 

 

Experience Hours (Planning & Scheduling): 
3200
Experience Hours (Cost Management): 
3200

Planning Manager, YAPI MERKEZI Construction, Morogoro-Makutupora SGR Railway Project

START Date: 
February, 2018
END Date: 
November, 2019

Planning and Monitoring of the project and supervision of planning team

site engineer/assistant planner, tutomaash, wembley car park , wembley stadium

START Date: 
March, 2017

Site Engineer/assistant planner

Setting out position and level  for ground beams and RC slabs.

all general activities about setting out engineering.

Carried out preparation, and the management of construction schedules. primavera p6 EPPM.

Tracked activities and prepared general project reports.

Constructed the Work Breakdown Structure(WBS)

Milestone,Critical Path, Earned value analysis and update as build program.

create and assign Resources, update progress/project. Maintain and Assign baseline.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
0

PLANNING ENGINEER, IMCO Engineering and Construction Co. WLL., Maintenance and Construction Project

START Date: 
August, 2008

A well presented and experienced PlanninG Engineer with over more than 9.8 years of extensive experience in the filed of Maintenance of Refinery Equipments and Execution and Shutdown Planning, Construction Project Oil and Gas Field, Oil and Gas Facilities Maintenance.

  • Planning and Scheduling
  • Maintenance of Refinery Equipments
  • Routine, Preventive ,Corrective and Shutdown Maintenance
  • Trunaround and Unscheduled Shutdown
  • Contstruction Project in Oil and Gas Field
  • Project Execuation
  • Material Management
Experience Hours (Planning & Scheduling): 
19650