Cost and Field Engineer, Newco Builder and Development Corporation, Various Hospitals and roads constructions

START Date: 
January, 1998
END Date: 
May, 2001

 

 

Experience Hours (Planning & Scheduling): 
3200
Experience Hours (Cost Management): 
3200

site engineer/assistant planner, tutomaash, wembley car park , wembley stadium

START Date: 
March, 2017

Site Engineer/assistant planner

Setting out position and level  for ground beams and RC slabs.

all general activities about setting out engineering.

Carried out preparation, and the management of construction schedules. primavera p6 EPPM.

Tracked activities and prepared general project reports.

Constructed the Work Breakdown Structure(WBS)

Milestone,Critical Path, Earned value analysis and update as build program.

create and assign Resources, update progress/project. Maintain and Assign baseline.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
0

PLANNING ENGINEER, IMCO Engineering and Construction Co. WLL., Maintenance and Construction Project

START Date: 
August, 2008

A well presented and experienced PlanninG Engineer with over more than 9.8 years of extensive experience in the filed of Maintenance of Refinery Equipments and Execution and Shutdown Planning, Construction Project Oil and Gas Field, Oil and Gas Facilities Maintenance.

  • Planning and Scheduling
  • Maintenance of Refinery Equipments
  • Routine, Preventive ,Corrective and Shutdown Maintenance
  • Trunaround and Unscheduled Shutdown
  • Contstruction Project in Oil and Gas Field
  • Project Execuation
  • Material Management
Experience Hours (Planning & Scheduling): 
19650

Assistant Planning Manager, Kuwaiti Manager's Company, Wadi Al Sail Mall, Al Mazaya Warehouse, Two nos. of 5 storey building, Isa town market restoration

START Date: 
May, 2013
END Date: 
July, 2014

Mostly involved in construction of a shopping mall with cinema and hypermarket facilities at Riffa, Bahrain. Other than that, was also handling programme and monitoring for a warehouse project with specialized flooring and a 5 storey building construction at Hidd. Project management work included maintaining cash-in and out flows for management on all active projects, and provide to accounting / finance to know budget and actual revenue earned and prepare CVC reports, tender master schedule and compilation of submission documents for tender.

Senior Planning Engineer (Acting Planning Manager), Gulf Technical Construction Company LLC - A Drake & Scull International PJSC, Reef Residence Tower

START Date: 
December, 2015

Senior Planning Engineer (Acting Planning Manager)

Projects: Main Contractor for current project, Reef Residence Tower (Value: $ 50 Million)

Experience Hours (Planning & Scheduling): 
4200
Experience Hours (Forensic Analysis): 
2500

Planning Engineer (Acting Senior Planning Engineer), Delta Al Emarate Building Contracting Company L.L.C., Al Fattan Tower and Tenora Hotel

START Date: 
March, 2015
END Date: 
November, 2015

Planning Engineer (Acting Senior Planning Engineer)  

Projects: Main Contractor for the projects - Al Fattan Tower (Value: $ 75 Million) and Tenora Hotel

Apartment (Value: $ 18 Million) respectively.

Experience Hours (Planning & Scheduling): 
1450
Experience Hours (Forensic Analysis): 
500

Planning Engineer (Acting Senior Planning Engineer), Commodore Contracting Company L.L.C., Abu Dhabi Office Tower & IPIC Tower

START Date: 
September, 2011
END Date: 
March, 2015

Planning Engineer (Acting Senior Planning Engineer)  

Projects: Main Contractor for the projects -  Abu Dhabi Office Tower (Value: $ 83 Million + Variations) and

Previously worked in IPIC Tower (Value: $ 270 Million + Variations) - International Petroleum Investment Company Project

Experience Hours (Planning & Scheduling): 
7500
Experience Hours (Forensic Analysis): 
2000

Project Control Manager | Superintendent, TOA Corporation, Breakwater & Cargo Pier

START Date: 
January, 2017

Preparation of Design, Construction, and Technical Submittals.

Preparation, Monitoring, and updating Project Schedule.

Preparation of Quality Control and Safety Manual & Procedure.

Preparation of Implementing Rules & Regulation.

Preparation of Monitoring of Project Quantity Survey.

Preparation of Progress Billig & Collection.

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500

Planning Engineer, Al-Farid Contracting Establishment, Residential, Buildings, Civil Works

START Date: 
December, 2003
END Date: 
September, 2007
Al-Farid Contracting Establishment is involved in the general construction of multi-storey commercial buildings and residential villas. • Prepare project schedules by Critical Path Method (CPM) including activity duration estimates, man-hours loading, Work Breakdown Structure (WBS), progress S-curve, monthly cash flow, and obtain approval of the Project Manager.
Experience Hours (Planning & Scheduling): 
4650
Experience Hours (Cost Management): 
2150
Experience Hours (Forensic Analysis): 
350

Planning Engineer / Project Scheduler, International Container Terminal Services, Inc., HEAD OFFICE

START Date: 
October, 2015

1.     Performs staff function to the Project Director and Project Managers regarding project schedule, monitoring and planning.

2.     Monitoring site for technical and progress reports/status.

3.     Maintains and updates project schedules.

4.     Preparation of comprehensive weekly and monthly progress reports

Experience Hours (Planning & Scheduling): 
2000

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes