Project Planning; Progress Reporting; Primavera P6; Master Schedule

Cost and Schedule Controls Manager/Scheduler/Coordinator, EPC Consultants, VTA/BART (SVBX) / Berryessa Extension Project $2.5 Billion- San Jose

START Date
END Date
Experience Hours (Planning & Scheduling)
1300
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
600

Senior Planning Engineer, Cairn Energy India Limited, Rajasthan Northern Development Project

START Date
END Date
Experience Hours (Planning & Scheduling)
2550

Senior Planning Engineer Rajasthan Northern Development Project.

The project consisted of a main process terminal (MPT) to handle 150, 000 bopd produced from 18 oil wells with water coming from 20km away and gas from 80km
Using P6 I administrated the database, set up user profiles and security, prepared the WBS and structured the activity codes for the level 3 integrated schedule.