1. Develop Windows Analysis both prospective and retrospective for the client
2. In the absence of contemporaneous updates, develop the monthly update windows based on linear distribution of progress
3. Research, cause and effect analysis
4. Develop fragnets and incorporate and use it to determine the impact of a delay event into the Time for Completion
5. Identifies issues that adversely impact progress for coordination
6. Manage the claims process
7 Attend claims meetings