Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Vietnam (AS.VN)

Conctract A Senior Planner, CMC/ITD/SONGDA, Laos, NamTheun 1 Hydro Power Project

START Date: 
November, 2016
END Date: 
May, 2018

Planner at NamThuen 1 Hydropower Project, Laos, Contract A with main tasks:

- Project planning (build project program with Primavera P6, update the program, analyse to extract critical paths and near critial paths, key performance index report, analyse project resources)

- EOT analysis

Experience Hours (Planning & Scheduling): 
4000

andie dt

First Name: 
andie
Last Name: 
dt
Oldest experience: 
Sep 2018 (6.7 yrs experience, WARNING: 48.7 years variance with Professional Since)
Years Experience: 
48

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Viet Tran

First Name: 
Viet
Last Name: 
Tran

- Preparation and monitoring of CPM schedules, preparing and monitoring progress curves, liaison between Owner and Contractor,

- Detail EV and EVMS reporting,

- Tracking and reporting physical progress and/or budger performance. Analyzing trends, issue predictable project scheduling,

- Develop/Prepare and/or assisting with WBS, EVMS, tracking/forecasting mechanisms,

- Building Project master schedule, integrated with contractor schedule. Create activity code, resource loaded, phase, etc.,

- TOEIC 800,

Professional Since: 
May-2008 (17.1 yrs experience)
Oldest experience: 
Jan 2016 (9.4 yrs experience, WARNING: 7.7 years variance with Professional Since)
Years Experience: 
48

PLANNING ENGINEER, China Huan Qiu Contracting & Engineering Corporation, Ninh Binh fertilizer factory project of Vietnam

START Date: 
June, 2009
END Date: 
August, 2011

 Worked as planning engineer in Ninh Binh fertilizer factory project of Vietnam from Jun 2009 to Aug 2011.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Market Place

No results found... (try selecting a different content filter)

Syndicate content