Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Saraya Aqaba Project

Planning Manager, CCC-DSC-ATC JV, Saraya Aqaba Project

START Date: 
July, 2013
END Date: 
January, 2016

Planning Manager Role: Reporting, Resource loading, Cost Loading, Cash Flow,

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
500

Project Controls Manager, Al Fadel Engineering & Contracting Co, Saraya Aqaba Project

START Date: 
November, 2008
END Date: 
December, 2009

 I was responsible for the following tasks :

 -Quantities Takeoff for different work items.

 -Preparation of Technical & Commercial Comparison Sheets for Procurement Department.

 -Preparation of the Monthly Project Payment Certificates.

 -Preparation, Revising & Updating the Project Baseline Schedules & Weekly Updates.

 -Preparation, Revising & Updating the Project Internal Target Schedules & Weekly Updates.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content