Fuqing Nuclear Power Plant Project

EPC Project Planning Specialist, CNNC China Nuclear Power Engineering Co., LTD., Fuqing Nuclear Power Plant Project

START Date: 
August, 2017
END Date: 
May, 2019
Main responsibilities:(1) Development and management of level 3 schedule in the EPC project;(2) Development and management of schedule database for the project;(3) Development and management of schedule management system in the project;Achievements:(1) Having developed and managed the master schedule for project with debugging 50 days in advance;(2) Having Been familiar with cons
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2050
Experience Hours (Forensic Analysis): 
2500