Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

scheduling

planning, Contol %26 Monitoring, scheduling, Planner/Progress Reporting/Cost Control Engineer, NABA, 132KV substations

START Date: 
August, 2009
END Date: 
August, 2013

Currently working on this project, scope of project is very wide with three substations, RIB buildings & Rubber laboratory. Here also I am single handedly planning& tracking the project master schedule, summary level curves. Also i am reporting weekly progress, daily progress, two weeks look ahead and involved in identification, monitoring & streamlining of critical path.

Scheduling, Al Khameen, Construction of Underpass

START Date: 
January, 2011

Working as a Planning Engineer. Main task is to prepare schedules of currently running projects of roads and bridges.

Project Planning, Scheduling, Control and Monitoring involved in various projects., M-IO Builders Sdn Bhd, Al Bidda Platinum Tower; Al Hitmi Office Building; Dubai Metro Stations

START Date: 
September, 2006
END Date: 
September, 2009

Job Description:

A.     Project planning, scheduling, control and monitoring involved in various projects such as:

A.1. M-IO Builders Qatar W.L.L.
Doha, Qatar

- Al Bidda Platinum Tower
2,300 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.

- Al Hitmi Office Building
1,700 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.
     
- Dubai Tower (Tender Document Preparation)

Scheduling, SAW, Program Management

START Date: 
June, 2003

Program Scheduler and Controls - import files into P6, update scheduled, advice on scheduling

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content