Assistant Manager - Project Management

Assistant Manager - Project Management, ONG Bel Avenir, Several, see above

START Date: 
May, 2017
END Date: 
June, 2017

Realization of agricultural experiments

Experience Hours (Planning & Scheduling): 
50

Assistant Manager - Project Management, DURACELL, IMPLEMENTATION OF CELL MANUFACTURING ASSMBLY LINES

START Date: 
March, 1986
END Date: 
March, 1989

In charge of supervising the adaptative design and erecting work of several cell manufacturing assembly lines in the plat facilities, including tolls and machines constructed loccally using basic design from USA and Netherlands plants.

In charge of mechanical and electrical maintenance supervising people working in shift hours

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
800

Assistant Manager - Project Management, Makati Development Corporation, SOLSTICE TOWER 1

START Date: 
April, 2007
EFCO Philippines Ltd Design Manager Overall In-charge of design and operation Macro Industrial Operations Manager Overall In-charge for operation of installation of precast Makati Development Corp. Design Supervisor Overall In-Charge for Design and operation of Formworks for Company wide operation. Makati Development Corp. Project In-Charge/ Construction Manager Overall In-Charge for Operations/ Construction of 43 storey bldg.

Assistant Manager - Project Management, MONTER SM, & Oil & Gas Projects

START Date: 
August, 2012

Project Manager on oil and gas pipelines and infrastructure projects

Assistant Manager - Project Management, MONTER SM, & Oil & Gas Projects

START Date: 
August, 2012

Project Manager on oil and gas pipelines and infrastructure projects

Assistant Manager - Project Management, MONTER SM, & Oil & Gas Projects

START Date: 
August, 2012

Project Manager on oil and gas pipelines and infrastructure projects

Assistant Manager - Project Management, MONTER SM, & Oil & Gas Projects

START Date: 
August, 2012

Project Manager on oil and gas pipelines and infrastructure projects.

Assistant Manager - Project Management, MONTER SM, & Oil & Gas Projects

START Date: 
August, 2012

Project Manager on oil and gas pipelines and infrastructure projects.

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date: 
March, 2007

Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections. Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports.

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date: 
March, 2007
Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections. Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports. Project documentation: Maintaining Delay record, Site Log, Hindrance register, Site order Book, Drawing register, RFI tracker, Site instruction tracker, NCR tracker, MOM tracker Meetings: Conducting Design review meetings, Progress review meetings, Escalation