Wood Group PSN

Senior Planning Engineer, Wood Group PSN, Offshore Oil & Gas Platform Refurb

START Date: 
December, 2013
END Date: 
June, 2014

Wood Group PSN, Runcorn

Senior Planning Engineer

Employed on a short term contract where I was responsible to the JRE and senior management of level 4 FEED programmes, and level 2, 3 & 4 installation and commissioning & handover phases on various refurbishment projects on the North Sea offshore oil and gas platforms. Main responsibilities include provision of manpower histograms, performance s-curves and weekly reports to senior management.

Experience Hours (Planning & Scheduling): 
1150

Hareen Marcelline

First Name: 
Hareen
Last Name: 
Marcelline

Ensuring plans and programmes are fully developed and tracked, coded in accordance with client agreed work breakdown structure.

Professional Since: 
May-1989 (30.4 yrs experience)
Oldest experience: 
May 1989 (30.4 yrs experience)
Years Experience: 
23

Senior Planning Engineer, Wood Group PSN, Total UK St Fergus Gas Plant & North Sea Assetts

START Date: 
March, 2014
END Date: 
August, 2014

Senior Planning Engineer - Team Member responsible to the Asset Focal Point Planning and Project Management Leads regarding Totals UK St Fergas Gas Plant Operations and North Sea Assetts

Experience Hours (Planning & Scheduling): 
1200
Experience Hours (Cost Management): 
50

Akhil R

First Name: 
Akhil
Last Name: 
R
Professional Since: 
Oct-2005 (14.0 yrs experience)
Years Experience: 
0

Cost & Schedule Engineer, Wood Group PSN, ExxonMobil - PNG LNG Project

START Date: 
November, 2013
END Date: 
March, 2015

Project planning and cost control of multiple small scale brownfield EPC projects (up to $5 million) across ExxonMobil's PNG assets, from project setup/initiation through to EPC execution complete and close-out.

Project Controls Engineer, Wood Group PSN, ExxonMobil - KTT Project

START Date: 
August, 2011
END Date: 
November, 2013

Project planning and cost control support for the brownfield EPC scope of ExxonMobil's KTT Project during the construction, commissioning/completions and close-out phases of Marlin Complex and West Tuna Platform/Kipper Subsea Facility tie-ins in Bass Strait, Victoria.

Gary Hampson

First Name: 
Gary
Last Name: 
Hampson
Oldest experience: 
Oct 2012 (7.0 yrs experience, WARNING: 42.7 years variance with Professional Since)
Years Experience: 
0

Lead/Senior Planning Engineer, Wood Group PSN, BP Focus

START Date: 
October, 2012

Senior Planning Engineer and Risk Manager looking after BP Focus brownfield contract

Lead/Senior Planning Engineer, Wood Group PSN, BP Focus

START Date: 
October, 2012

Senior Planning Engineer and Risk Manager looking after BP Focus brownfield contract

Asset Planner, Wood Group PSN, BP Focus

START Date: 
January, 1994

Experience of working in the Petro Chemical / Oil & Gas industry since Jan 1994. A results oriented individual with technical ability and an established track record in the delivery of Planning support. Able to manage changing priorities on a variety of projects at any one time, to meet deadlines. Able to adopt an energetic and enthusiastic approach in key service goals and performance targets.

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content