Planning Lead, Sonangol, D-111

START Date: 
March, 2008
END Date: 
March, 2009

ADCTX                                                                                                                       March 2008 – March 2009

Morsa West Field Development 

Dolphin D-111 Rebuild, Transit, Installation, HUC                         

Angola, Africa                                                                                                    

Project Scheduling Lead

 

Develop and manage overall plan and schedule in P6.  Set the schedule activities weighted value, baseline schedule and report progress against the baseline.  Integration of drilling, diving / sub-sea and commissioning schedules into the overall master schedule.  Additionally, I was responsible for resource loading and P.O.B. forecasting around the constraints of limited bed space in order to achieve first oil in a safe and timely manner.