Level of Effort for Indirect Costs

D
Dennis Hanks 👤 Member for 19 years 2 months

Dieter;



Right, but in my case I use ’fixed units’ and the LOE/Hammock activity moves as the underlying activities move - just as I was hoping.

D
Dieter Wambach 👤 Member for 19 years 5 months

Dennis



I don’t know your understanding of "regular".



For resource assignments you have a parameter

"calculate cost from units" Switch off, then costs will be indepentent from units



On activity level: duration type set to "fixed duration and units", then units will remain constant independent from the duration.



Regards

Dieter

D
Dennis Hanks 👤 Member for 19 years 2 months

Kieran;



Thanks for the reply, but what I was after was whether or not a P6 LOE activity behaved as a ’regular’ activity. That is, would it’s costs change as it’s duration changed driven by the underlying activities.



In Pertmaster, LOE activities are called hammocks and do behave as expected, so indirect costs can be effectively modeled.



Again, thanks for the input.

K
Kieran Thomson 👤 Member for 22 years 4 months

Not really up with this sort of request so I’ll give it my best.



If the delay you are talking about has a direct effect on the critical path then yes, or no, depending on the contract you have signed into.

But usually yes if it critical connected.

Indirect cost poses more questions, therefore if company thinks they are delayed, get time booking, receipts, charges, all sorts. If your company bean counters arent up to it your basically fucked as a company. Bail.

D
Dieter Wambach 👤 Member for 19 years 5 months

Dennis



"fixed units" and "fixed duration and units" for LoE has the same behaviour because they have no own duration.

Forum Sponsor

Top Posters

Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts