Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Delay in p6

8 replies [Last post]
haytham saad
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24

Hi every one

can  Actrivitiy Has a delay in days more than the Updating interval ex.: if th update Int.=30days

after update can the activity has more than 30 days delay greater than the previous delay ???

Replies

Rafael Davila
User offline. Last seen 3 hours 14 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Reverse Logic might allow this to happen without using negative lag and without being OOS progress. Technically it cannot be OOS progress as it has not even progressed! Try it yourself.

 photo Reverse Logic_zpsk2j732ub.png

Kannan CP
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

it is possible to have the activity starts before the completion of predecessor.It is out of sequence activity.

 

Regards

Kannan

Atif Mehmood
User offline. Last seen 7 years 29 weeks ago. Offline
Joined: 29 Sep 2016
Posts: 3
Groups: None

Good afternoon all,

Is it possible, actual start date of activity earlier than his predecessors milestone.

Thanks.

Atif Mehmood
User offline. Last seen 7 years 29 weeks ago. Offline
Joined: 29 Sep 2016
Posts: 3
Groups: None

Good afternoon all,

Is it possible, actual start date of activity earlier than his predecessors milestone.

Thanks.

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes there are many ways. 1. The remaining durations along the critical are now greater than the previous update for whatever reason. 2. You have increased a duration because of a long lead time item deliver date has changed. 3. You made major logic changes which increased the total length of the critical path. 4. You are now working 5 days per week instead of 6 days per week. Of course all of these scenarios this work is or now is on the critical path. 6. you now have an earlier project must finish by date. 7. You inserted an start no earlier than date into your schedule which became critical. 8. You don't have enough resources and your resources are driving the durations. 9. Last month you overstated your progress and now you have to make some adjustment to your % complete which in turn increases your remaining durations.

Tom Boyle
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Haytham,

There is not much to improve on Robert Bell's answer to your initial question.  As to your follow-up question:

Absent any other changes, in P6, the early finish will be the Remaining Duration + Remaining Early Start.  For an in-progress activity, Remaining Early Start will be the same as Data Date unless it has been pushed out by retained logic (i.e. an unsatisfied predecessor) or some other constraint (including Suspend/Resume).  In either case you would easily see this, as the uncompleted part of the bar on the Gantt chart will move away to the right of the data date.

The task calendar may also have an increase in non-working time during the upcoming month (compared to last month).  This can make your early finish date later than you expect (but your expectation would have been wrong.)

Good luck, tom 

haytham saad
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24

Hi Robert

thnx for ur answer but beside these issue if i dont do any of them and no progress in the activity does the new finish date expected = remaing duration +Data date ??

Robert Bell
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Haytham,

Sure activities can have greater delays than the update period. Changing the logic, adding constraints, or increasing remaining durations; any of these can lead to greater slips in a period than the period itself.