How to convert MPP file to XER or MPX

hello house,

please does anyone know how to convert mpp to xer or mpp to mpx,

as whenever i import mpp to xer on primavera, i get error message as such he does not import.

 

am using P6,8.2

is there a software or any way around this

 

thanks

tony

Z
Zoltan Palffy 👤 Member for 17 years

I AM AMMENDING MY POST SINCE A NEW PRODUCT HAS COME TO THE MARKET.

NEW OPTION #1 USE XERTRANSFER UTILITY  

https://xertransfer.com/ 

option #1

Primaver has a mpp to mpx converter

here is the link

https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing Option #2

save the file as an MPX

Option #3

convert the file from an MPP to a PPR then from a PPR to and MPX

here is the link for the free softwate 

http://smartworks-mpp-2-ppr-converter.software.informer.com/4.0/

 

So, here is the tool help you to convert MPP to MPX.

https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

Nowadays, Microsoft Project save file as MPP format. However Primavera allow to import file as MPX format.

So, here is the tool help you to convert MPP to MPX.

https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

 

Z
Zoltan Palffy 👤 Member for 17 years

you have several options 

option #1 

Primaver has a mpp to mpx converter

here is the link

 
Option #2

save the file as an MPX

Option #3

convert the file from an MPP to a PPR then from a PPR to and MPX

here is the link for the free softwate 

http://smartworks-mpp-2-ppr-converter.software.informer.com/4.0/

 

So, here is the tool help you to convert MPP to MPX.

https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

Nowadays, Microsoft Project save file as MPP format. However Primavera allow to import file as MPX format.

So, here is the tool help you to convert MPP to MPX.

https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

Featured Partner

Top Posters

yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts

Our Partners