Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

%100 Project Planning; Performance Monitoring; Project Control; P6 Scheduling

LEAD PROJECT PLANNING ENGINEER, Chaleun Sekong Energy Company Limited – Laos , Nam Kong 3 Hydro Power Plant Project

START Date: 
June, 2018
  • Prepare  the Master Program and all works programs based for the project.

 

  • After awarding to Contractors, establish the required documents and reports needed to ensure a  proper manage and control of the works. such as the Contractors’ planned resources and production s-curves, progress evaluation forms, submission s-curves, earned-value  for works form and other.

 

  • Provide information to the project team about the Overall Progress, as well as by Main Work Areas.

 

LEAD PROJECT PLANNING ENGINEER, CMC di Ravenna Construction Ltd., The Angat Water Transmission Improvement Project

START Date: 
April, 2016
END Date: 
May, 2018
  • Manage the Internal Programme for the Construction Team;  and the Contractual Programme for the Project Stakeholders
  • Preparation of target programs and short term rolling programs aligned to the internal master programme
  • Prepares weekly and monthly progress reports for the Project Manager, to be submitted to the Client
  • Attend Weekly Coordination Meetings with the Client to update the status of works and highlight possible risks and obstacles of the construction.
  • Compile data for possible delay claims
  • Prepare Delay Impact  analysis by Gr

Senior Planning and Scheduling Engineer, Exyte Malaysia, First Solar KMT-2 Project

START Date: 
November, 2017
Projects: 1. First Solar KMT-2 Project – First Solar, Kulim Plant. Design and modification of Module 3 & 4 to suite production upgrade from series 4 to series 6 solar panels. 2. First Solar KMT-1 CDA Expansion Project – First Solar, Kulim Plant Design and modification of CDA System to suite newly ugraded VTD coater requirements. 3. VerdePalm Project – Verdezyne, Johor Malaysia EPCC of civil, structural, architectural, mechanical, electrical, controls and instrumentation.
Experience Hours (Planning & Scheduling): 
2900

Schedule/Progress and Ratio Engineer, SAIPEM TAQA ALRUSHAID FABRICATORS, 000 for construction)

START Date: 
February, 2009
END Date: 
December, 2010
  • Monitor in weekly basis progress report to manager and analysis.
  • Study and estimate fabrication hours require for doing any job and evaluate in parallel.
  • Manage and Control project as plan schedule to avoid delay.
  • Define fabrication method.
  • Analyze isometric drawing for fabrication.
  • Issuing martial for fabrication.
Experience Hours (Planning & Scheduling): 
3600
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
1000

Planning & Project Control Manager, PETROFAC ENGINEERING, Yibal khuff Project

START Date: 
July, 2015

Porject control manager responsible for Oil & Gas project consisting of Oil treatment, Gas treatment and Sulhpur recovery

Senior Primavera Support Specialist, Exxon Mobil, Fawley Refinery Turnarounds and Events

START Date: 
January, 2013
Senior Primavera P6 Scheduler / Planner Supervisor Main Responsibilities: Help set up a new Programmes Event Team to undertake small yearly outage which the turnaround team used to undertake. This was initial a three person group made up of a Superintendent, Primavera planner/scheduler and a lead field engineer. Due to my SAP back ground I was asked to learn Primavera and set up this role as I saw fit.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
2000

Programme Planning Engineer, National Grid, (various projects)

START Date: 
March, 2015

Programme Planning Engineer - National Grid

 

Building P6 schedules from scratch / from templates in the project development phase

Resource and budget-loading

Making monthly updates

Obtaining progress updates from project team members

Producing reports for project team members

Undertaking deliverability assessments

Creating and maintaining baselines

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

planner, CSPC, Petro-Chemical/Oil & Gas

START Date: 
August, 2009
END Date: 
April, 2010

CSPC is a joint ventre of CNOOC and shell company. I worked there on it's Debottlenecking and Turnaround project as a planner,developing and tracing DB&TA plan of the EO/EG facility.

Experience Hours (Planning & Scheduling): 
1200

Construction Scheduling & Planning Consultant, MDCD Corporation, NY, USA, NYCSCA, NYCT, NYCDEP, NYCDOT, NYSDOT, NYCDDC

START Date: 
October, 2001
END Date: 
October, 2017
Michael Dellaquila    
Dix Hills, NY 11746
mdellaquila@mdcdcorp.com    
      
WORK HISTORYCPM Scheduling Consultant/Owner of MDCD Corp. (September 2010 - Present)
• Project Estimating, Cost Analysis, Bidding, Purchasing, Expediting, CPM Scheduling, Project Analysis, Project Controls,
• Build New and Repair Current CPM construction Schedules, CPM Schedule Time Extensions
Experience Hours (Planning & Scheduling): 
24950
Experience Hours (Cost Management): 
15550
Experience Hours (Forensic Analysis): 
4200

Lead Planner, Lundin Gold, Fruta del Norte

START Date: 
March, 2017

Planning, Scheduling and Progress Meas

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
100

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content