Project Planner / Forensic Planner, CMC di Ravenna, Cornubia Interchange to Meridian Drive, Durban

START Date: 
August, 2015
END Date: 
June, 2017
  • To revise the POW for the changes & to schedule unforeseen works & activities.
  • To assist the Production Team in making strategies to attempt different activities so as to reduce both the time and cost.
  • To analyze and study the delays, time loses and additional works and to work out for the EOT claims.
  • Time Impact Analysis & Reports for EOT Claims.
  • To revise & update the cash flow.
  • To prepare the Internal WBS (Work Breakdown Structure) of different activities to insure better monitoring and boosted progress.
  • Early warning o

Project Planner / Forensic Planner, CMC di Ravenna, Improvements to the MT. Edgecombe Interchange (Km 3.7)

START Date: 
August, 2013
END Date: 
June, 2017
  • To revise the POW for the changes & to schedule unforeseen works & activities.
  • To assist the Production Team in making strategies to attempt different activities so as to reduce both the time and  cost.
  • To analyze and study the delays, time loses and additional works and to work out for the EOT claims.
  • Time Impact Analysis & Reports for EOT Claims.
  • To revise & update the cash flow.
  • To prepare the Internal WBS (Work Breakdown Structure) of different activities to insure better monitoring and boosted progress.
  • Early war

Gerard Van der Merwe

First Name: 
Gerard
Last Name: 
Van der Merwe

25 years’ experience in multi-discipline contract management, setting-up all project control processes throughout the Project life cycle models. Experience include International Federation of Consulting Engineers is (FEDIC) and New Engineering Contract (NEC) management.

Professional Since: 
Jan-2005 (15.0 yrs experience)
Years Experience: 
0

Rick Louw

First Name: 
Rick
Last Name: 
Louw
Professional Since: 
Oct-2006 (13.2 yrs experience)
Years Experience: 
0

Stephen Enslin

First Name: 
Stephen
Last Name: 
Enslin
I have been working on Exxaro Mine in Limpopo for the last 6 years in the Project Team.We have worked with Multi-Discpline projects over the 6 years. Duties that we have to dois progress reports weekly or monthly. S-Curves and Histrograms per project set up theMaster schedule and update daily and weekly.
Professional Since: 
Sep-2008 (11.3 yrs experience)
Oldest experience: 
Jan 2007 (13.0 yrs experience, WARNING: 1.7 years variance with Professional Since)
Years Experience: 
9

Project Planner, Redis Construction Afrika (Pty)Ltd, Nickel Tank House Rustenberg

START Date: 
September, 2008
END Date: 
February, 2009

Project Planner, Redis Construction Afrika (PTY) Ltd

In this role I was a Project Planneron Multi Discipline project where i worked on Primavera P3, Resource Loading  was done by myself as well as the Supervisors. I worked closely with Material Control as to see what stock had been brought to site and what else was needed to order to complete the Project.

Experience Hours (Planning & Scheduling): 
1100

Project Planner, Time Mining (PTY) Ltd, Time Mining (PTY)Ltd

START Date: 
March, 2009
END Date: 
February, 2012

Project Planner, Time Mining (PTY)Ltd

I was Project Planner on a Multi Discipline Projects, I Worked on Primavera P3 and MSP, Resource loading wasdone by myself. Weekly updates on P3 and MSP were done. I Also worked withe Procurement Office to get a better understanding of the procurement process as well as placing of orders and arrangement of shipment of good the Middle Africa.  

Experience Hours (Planning & Scheduling): 
5750

Project Planner, Wade Walker, GMEP

START Date: 
April, 2012
END Date: 
September, 2012

Project Planner, Wade Walker on GMEP Grootegeluk Mine in Lephalale.

In this role I worked on Primavera 6, responsible for Resource loading was done by myself as well as the development and updating of Histrogram, S-Curves and Look-A-Heads. I used P&ID's to update and to follow progress. 

Experience Hours (Planning & Scheduling): 
1100

Project Planner, Exxaro, Project Team

START Date: 
October, 2012

Current Position : Project Planner , Exxaro Grootegeluk Coal Mine


In this role my duties include Microsoft Projects Scheduling, Forecasting, Resource Loading and Earned Value. There is close cooperation between the Project Manager and myself. Weekly deliverables include Histrograms, S-Curvesand Look-A-Heads.

 

Competencies Development:

In my positon as Project Plannerat Exxaro I'm faced with many challenges which require from me sevaral Competencies.

Experience Hours (Planning & Scheduling): 
10000

Craig Penn-Clarke

First Name: 
Craig
Last Name: 
Penn-Clarke

We have developed Software, aimed specifically at the Pipe Fabricator and/or Pipe Erector.

This software allows for most resources within an organisation to enter data from the ISO drawing, accuratly and timeously.  With multiple users on our web-based platform, we can enter huge volumes of data in a seamless and structured mannor

The software generates every activity, adds resources, time, linkages, equipment used etc that is imported into scheduling software (such as MS Project) via an Excel file / map.

Professional Since: 
Jun-1984 (35.5 yrs experience)
Years Experience: 
0

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.