P6 Integration API for running data exchange
Mon, 2012-08-06 11:00
I want to show my schedule from Primavera as Time-Distance-Diagram in TILOS. To get the data-exchange running it seems that you need to install P6 Integration API first?
Thu, 2012-09-06 23:30
#1
There are several methods to get data from P6 to Tilos, the API is one of them. I find the clipboard method the simplest and does not need the API.