P6 Integration API for running data exchange

1 reply [Last post]
nurullah erel
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 9 Jul 2012
Posts: 6
Groups: None

I want to show  my schedule from Primavera as Time-Distance-Diagram in TILOS. To get the data-exchange running it seems that you need to install P6 Integration API first?

Replies

Paul Harris
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 11 Apr 2001
Posts: 609

There are several methods to get data from P6 to Tilos, the API is one of them. I find the clipboard method the simplest and does not need the API.

 

 

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com