Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

RECOVERY PLAN

6 replies [Last post]
Sohayle Pasandalan
User offline. Last seen 4 years 41 weeks ago. Offline

Gents,

Anybody who can explain to me a RECOVERY PLAN?

SPP

Replies

Sohayle Pasandalan
User offline. Last seen 4 years 41 weeks ago. Offline

Mr Gary,

Thanks...

Gary Whitehead
User offline. Last seen 4 years 43 weeks ago. Offline

A recovery plan can mean a number of things, and before issuing one, it is important to consult the contract and/or client to understand which one applies:

1) A revised programme to recover contractor delays to the forecast completion, of the project or project stage, costs to be met by the contractor

2) A revised programme to recover client delays to the forecast completion, of the project or project stage, costs to be met by the client (ie an instruction to accelerate)

3) A revised programme to recover all delays to the forecast completion, of the project or project stage, costs to be met by the contractor

4) A revised programme to recover all delays to the forecast completion, of the project or project stage, costs to be met by the client

5) In contract forms where the logic / durations / calendars /constraints cannot normally be ammended after client approval, a revised programme to recover as much delay as possible at zero cost (this will normally be the contractor's working programme or optimistic schedule)

It is good praxctise and benfits both contractor and client if any outstanding EOT claims are resolved prior to this excercise so both sides understand the full implications of the recovery programme. This is not always possible but should at least be attempted.

A couple of other points to bear in mind:

-If the cost to the contractor of recovering the delay are larger than the financial penalties for late completion, it may not be desirable to commit to a recovery programme

-If some or all of the delays to be recovered are client delays, check with the client as to what, if anything they can do to help (e.g. shorter client approval periods, relaxed quality control procedures, etc)

-Sometimes forecast delay can be recovered by increasing risk (e.g. placing an order before final approval). It is important to understand who bears the costs of such risks.

Sreejish Vishnu
User offline. Last seen 11 years 2 weeks ago. Offline
Joined: 11 Nov 2005
Posts: 32
Groups: GPC Qatar

Hi,

it depends on what is your eligibility for extension over. suppose your eligibility is for 40 days and the overall delay on project is 60 days. in that case you can make a recovery programme which can have a finish date 40 days late from the original programme. ie. recovering the 20 days culpable delays.

 

Sohayle Pasandalan
User offline. Last seen 4 years 41 weeks ago. Offline

...

Daniel Limson
User offline. Last seen 4 years 35 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Please note that a recovery programme, should be backed up by resources. There are only 2 ways to recover lost time and that is by increasing your resources or extending your working hours or adding night shifts. Work around or re-squencing your activities may gain you some time but production wise will still be the same.

Sreejish Vishnu
User offline. Last seen 11 years 2 weeks ago. Offline
Joined: 11 Nov 2005
Posts: 32
Groups: GPC Qatar

Hi sohayle,

When the Project progress is delayed as against the Contract programme, the Owner can request for a recovery schedule. The Contractor can change the sequencing of the activities or the duration of the activities to meet the original project completion date and the revised programme could be submitted as a recovery programme. However, the term recovery schedule is used mostly used with regards to recovering the Contractor's culpable delays. So, the recovery schedule is requested so as to recover the culpable delays by the Contractor and the submission of recovery schedule to a certain extent will be like the Contractor's admission of his delays.

On the other hand, if the contractor has an EOT request  in place and the Contractor believes he has an entitlement for EOT, then the recovery schedule request could be treated as a request for constructive acceleration, provided, the Contractor  gives notice to the client stating that their request for recovery schedule would be considered subject to additional cost.