Methods of Construction (C. INTERIORS)

5 replies [Last post]
hussein obey
User offline. Last seen 13 years 5 weeks ago. Offline
Joined: 22 Jun 2005
Posts: 30
Dear All,

Reference to my previous posting for Methods of Construction and that no one has shared the issue except for "Sukumaran Subaramaniyan" who advised to breack down the subject and to focus on objectives.

Our objectives are to formulate the method statement for different construction project items as a step towards standardizing scheduling practice. Then to publish this manual among all planning planet members to be circulated as a property for planning planet community.

We here are talking about "C. INTERIORS" which as a start may be brokedown as follows:

C. INTERIORS
C10 Interior Construction
C1010 Partitions
C1020 Interior Doors
C1030 Specialties
C20 Staircases
C2010 Stair Construction
C2020 Stair Finishes
C30 Interior Finishes
C3010 Wall Finishes
C3020 Floor Finishes
C3030 Ceiling Finishes

This is our project and you all will be proud of it.

Thank you,

Your’s,
Hussein, M.Sc. in construction management.
hamaksoud@yahoo.com

Replies

Milind Pandhare
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
Activity ID Activity description
MOBI-01 Site Mobilisation
MOBI-03 Fencing work
MOBI-02 Establish Temporary Servicies
EARTH-03 Shoring ( I- Section Concrete pannel )
EARTH-02 Priliminary Earth Work
EARTH-04 1st Phase Excavation
EARTH-05 2nd stage Excavation & concrete panel instlation
EARTH-07 Carting Excess Excavated material
EARTH-06 Dewaterring
EARTH-08 Formation of Deep Area
EARTH-09 Compaction & Formation for Raft bed
FOUND-02 Guniting
FOUND-01 PCC Deep Area
FOUND-03 PCC below RAFT
FOUND-05 Rubberised Bitumen Coating
FOUND-06 Waterproofing & Screed Protection
FOUND-04 Vertical area water proffing
FOUND-07 Steel work for RAFT
MEP-01 Drainage pipe laying and testing (UG Drainage)
FOUND-08 Raft Slab Casting (Part A&B)
SUB-01 Retaining Wall
SUB-06 Ramp Work
SUB-02 Shear Wall & Lift Core Wall
SUB-03 steel work for column
SUB-04 Form work for column
SUB-05 Column casting For GF Slab
SUB-07 Decking Work for G.F Slab
SUB-08 Steel Work for G.F Slab
SUB-09 MEP sleves & conduits for G.F Slab
SUB-10 Ground Floor Slab Casting
SUB-11 Deshuttering
SUB-12 Ramp Side RCC wall
SUB-13 Rcc planters & side wall / upstaand
SUCO-GF-02 steel work for column/A
SUCO-GF-03 Form work for column/A
SUCO-GF-01 Shear Wall /A
SUCO-GF-04 Column casting For 1F/A Slab
SUCO-GF-05 Decking work for 1F/ASlab
SUCO-GF-07 Steel Work for 1F/A Slab
SUCO-GF-08 MEP sleves & conduits for 1.F/A Slab
SUCO-GF-09 First Floor Slab Casting[Part-A ]
SUCO-GF-10 Deshuttring PART- A
SUCO-GF-12 steel work for column
SUCO-GF-11 Shear Wall & Lift Core Wall
SUCO-GF-13 Form work for column
SUCO-GF-14 Column casting For 1F Slab
SUCO-GF-15 Decking work for 1F Slab
SUCO-GF-17 Steel Work for 1F Slab
SUCO-GF-18 MEP sleves & conduits for 1.F Slab
SUCO-GF-19 First Floor Slab Casting[Part-B ]
SUCO-GF-20 Deshuttering PART- B
SUCO-GF-16 Ramp Side RCC wall
SUCO-1F-01 steel work for column/A
SUCO-1F-02 Form work for column/A
SUCO-1F-03 Shear Wall /A
SUCO-1F-04 Column casting For 2F/A Slab
SUCO-1F-05 Decking work for 2F/ASlab
SUCO-1F-06 Steel Work for 2F/A Slab
SUCO-1F-07 MEP sleves & conduits for 2.F/A Slab
SUCO-1F-08 Second Floor Slab Casting[Part-A ]
SUCO-1F-09 Deshuttering PART- A
SUCO-1F-11 Steel work for column
SUCO-1F-12 Form work for column
SUCO-1F-10 Shear Wall & Lift Core Wall
SUCO-1F-13 Column casting For 2F Slab
SUCO-1F-14 Decking Work for 2F Slab
SUCO-1F-15 Steel Work for 2F Slab
SUCO-1F-16 MEP sleves & conduits for 2 F Slab
SUCO-1F-17 Second Floor Slab Casting [Part-B ]
SUCO-1F-18 Deshuttering PART- B
SUCO-2F-01 steel work for column/A
SUCO-2F-02 Form work for column/A
SUCO-2F-03 Shear Wall /A
SUCO-2F-04 Column casting For 3F/A Slab
SUCO-2F-05 Decking work for3F/ASlab
SUCO-2F-06 Steel Work for3F/A Slab
SUCO-2F-07 MEP sleves & conduits for 3 F/A Slab
SUCO-2F-08 ThirdFloor Slab Casting[Part-A ]
SUCO-2F-09 Third floor slab Deshuttering PART- A
SUCO-2F-11 steel work for column
SUCO-2F-10 Shear Wall
SUCO-2F-12 Form work for column
SUCO-2F-13 Column casting For 3F Slab
SUCO-2F-14 Decking Work for 3F Slab
SUCO-2F-15 Steel Work for 3F Slab
SUCO-2F-16 MEP sleves & conduits for 3F Slab
SUCO-2F-17 Third Floor Slab Casting [Part-B]
SUCO-2F-18 Deshuttering PART- B
SUCO-3F-01 steel work for column/A
SUCO-3F-02 Form work for column/A
SUCO-3F-03 Shear Wall /A
SUCO-3F-04 Column casting For 4F/A Slab
SUCO-3F-05 Decking work for 4F/ASlab
SUCO-3F-06 Steel Work for4F/A Slab
SUCO-3F-07 MEP sleves & conduits for4.F/A Slab
SUCO-3F-08 Fourth Floor Slab Casting[Part-A ]
SUCO-3F-09 Deshuttering PART- A
SUCO-3F-11 steel work for column
SUCO-3F-10 Shear Wall & Lift Core Wall
SUCO-3F-12 Form work for column
SUCO-3F-13 Column casting For 4F Slab
SUCO-3F-14 Decking Work for 4F Slab
SUCO-3F-15 Steel Work for 4F Slab
SUCO-3F-16 MEP sleves & conduits for 4F Slab
SUCO-3F-17 Fourth Floor Slab Casting [Part-B
SUCO-3F-18 Deshuttering 4 F slab PART- B
SUCO-4F-01 steel work for column/A
SUCO-4F-02 Form work for column/A
SUCO-4F-03 Shear Wall /A
SUCO-4F-04 Column casting For5F/A Slab
SUCO-4F-05 Decking work for 5F/ASlab
SUCO-4F-06 Steel Work for 5F/A Slab
SUCO-4F-07 MEP sleves & conduits for 5F/A Slab
SUCO-4F-08 Fifth Floor Slab Casting[Part-A ]
SUCO-4F-09 Deshuttering PART- A
SUCO-4F-11 steel work for column
SUCO-4F-10 Shear Wall & Lift Core Wall
SUCO-4F-12 Form work for column
SUCO-4F-13 Column casting For 5F Slab
SUCO-4F-14 Decking Work for 5.F Slab
SUCO-4F-15 Steel Work for 5.F Slab
SUCO-4F-16 MEP sleves & conduits for 5.F Slab
SUCO-4F-17 Fifth Floor Slab [Part-B]
SUCO-4F-18 Deshuttering 5F Slab PART- B
SUCO-5F-01 steel work for column/A
SUCO-5F-02 Form work for column/A
SUCO-5F-03 Shear Wall /A
SUCO-5F-04 Column casting For 6F/A Slab
SUCO-5F-05 Decking work for 6F/ASlab
SUCO-5F-06 Steel Work for 6F/A Slab
SUCO-5F-07 MEP sleves & conduits for 6 F/A Slab
SUCO-5F-08 Sixth Floor Slab Casting[Part-A ]
SUCO-5F-09 Deshuttering PART- A
SUCO-5F-11 steel work for column
SUCO-5F-10 Shear Wall & Lift Core Wall
SUCO-5F-12 Form work for column
SUCO-5F-13 Column casting For 6 F Slab
SUCO-5F-14 Decking Work for 6.F Slab
SUCO-5F-15 Steel Work for 6.F Slab
SUCO-5F-16 MEP sleves & conduits for 6.F Slab
SUCO-5F-17 Sixth Floor Slab Casting PART-B
SUCO-5F-18 Deshuttering PART- B
SUCO-6F-01 steel work for column/A
SUCO-6F-02 Form work for column/A
SUCO-6F-03 Shear Wall /A
SUCO-6F-04 Column casting For 7F/A Slab
SUCO-6F-05 Decking work for 7F/ASlab
SUCO-6F-06 Steel Work for 7F/A Slab
SUCO-6F-07 MEP sleves & conduits for 7F/A Slab
SUCO-6F-08 Seventh Floor Slab Casting[Part-A ]
SUCO-6F-09 Deshuttering PART- A
SUCO-6F-11 steel work for column
SUCO-6F-10 Shear Wall & Lift Core Wall
SUCO-6F-12 Form work for column
SUCO-6F-13 Column casting For 7F Slab
SUCO-6F-14 Decking Work for 7.F Slab
SUCO-6F-15 Steel Work for 7.F Slab
SUCO-6F-16 MEP sleves & conduits for 7.F Slab
SUCO-6F-17 Seventh Floor Slab Casting (PART-B)
SUCO-6F-18 Deshuttering PART- B
SUCO-7F-01 steel work for column/A
SUCO-7F-02 Form work for column/A
SUCO-7F-03 Shear Wall /A
SUCO-7F-04 Column casting For RF /A Slab
SUCO-7F-05 Decking work for RF/A Slab
SUCO-7F-06 Steel Work for RF/A Slab
SUCO-7F-07 MEP sleves & conduits for RF/A Slab
SUCO-7F-08 Roof Floor Slab Casting[Part-A ]
SUCO-7F-09 Deshuttering PART- A
SUCO-7F-11 steel work for column
SUCO-7F-10 Shear Wall & Lift Core Wall
SUCO-7F-12 Form work for column
SUCO-7F-13 Column casting For RF Slab
SUCO-7F-14 Decking Work for R.F Slab
SUCO-7F-15 Steel Work for R.F Slab
SUCO-7F-16 MEP sleves & conduits for R.F Slab
SUCO-7F-17 Roof Slab Casting (PART-B)
SUCO-7F-18 Deshuttering PART- B
SUCO-HC-01 steel work for column
SUCO-HC-02 Shear Wall & Lift Core Wall
SUCO-HC-03 Form work for column
SUCO-HC-05 Parapet Wall
SUCO-HC-04 Column casting
SUCO-HC-07 Swimming pool Shell
SUCO-HC-10 Pool Deck
SUCO-HC-06 Decking Work for HC Slab
SUCO-HC-09 MEP sleves & conduits for HC Slab
SUCO-HC-08 Steel Work for HC Slab
SUCO-HC-11 Helth Club Slab Casting
SUCO-HC-12 Deshuttering
SUCO-UR-03 steel work for column
SUCO-UR-02 Shear Wall & Lift Core Wall
SUCO-UR-04 Form work for column
SUCO-UR-05 Parapet Wall above HC
SUCO-UR-01 Column casting For lift m/c room
SUCO-UR-06 Decking Work for lift m/c room
SUCO-UR-08 MEP sleves & conduits for lift m/c room
SUCO-UR-07 Steel Work for lift m/c room
SUCO-UR-09 Lift m/c room Slab
BLO-B-01 cleaning
BLO-B-02 Block layout and checking
BLO-B-03 Block work in Basement
BLO-B-04 R.C.C Lintel
PLAS-B-01 Wall Plaster - Basement
PLAS-B-02 Celing Plaster-Basement
FLO-B-02 marble flooring to lift loby
A0EXAV-09 Earth filling above raft 8’’tk
FLO-B-04 Marble Wall Clading to Lift Loby
FLO-B-05 4’’ PCC with mesh
FLO-B-07 Pump/ Store room flooring
FLO-B-01 Car parking /Driveway Floor Finishing
FLO-B-03 floor finish to water tank area
FLO-B-06 Wall clading to Pump room
FLO-B-08 Thrishold
FAL-B-01 False Ceiling
PANT-B-01 Internal wall & ceiling painting
PANT-B-02 Anticarbonation painting in wall
PANT-B-03 Final internal painting
CARP-B-01 Fixing of Door Frame
CARP-B-02 Fixing of Door Shutter
A0MIS-01 Substation Trenching Work
MET-01 Aluminium (LOUVER WORK) Substation
PANT-GF-01 Transformer room painting
A0PRO-17 Dewa Inspection Substation
A0PRO-18 Sub station hand over to DEWA
BLO-GF-01 cleaning
BLO-GF-02 Block layout and checking
BLO-GF-03 Internal Block Work
BLO-GF-04 Block work- GF
A0ON-GF-08 R.C.C Lintel
PLAS-GF-02 Celing Plaster- GF
PLAS-GF-01 Wall Plaster GF
WPR-GF-02 GF- Parking W/P
WPR-GF-01 Water proof coating to Wet areas
WPR-GF-03 Vertical side w/p of wet area
FLO-GF-08 Wet area wall clading ( garbage room)
FLO-GF-06 Wet area flooring (ceramic tiles)
WPR-GF-04 Water proofing to substation slab roof
FLO-GF-02 Floor Screed for Electrical Room/gym/
FLO-GF-01 4’’ PCC with mesh
FLO-GF-03 Floor Screed for M.hall
FLO-GF-05 Floor Screed for Electricaal Sub-station
FLO-GF-04 Car parking /Driveway Floor Finishing
FLO-GF-07 Floor Screed for Gym / Shop
FLO-GF-09 Mosaic flooring to stair floor & landing area
FLO-GF-10 Floor Screed for Gen. Room
FLO-GF-11 Store and other room flooring
FLO-GF-12 mosaic step
FLO-GF-14 Marble flooring to Entrance passage
FLO-GF-15 mosaic skirting for steps
FLO-GF-13 Threshold
FLO-GF-17 Fixing Marble Steps
FLO-GF-16 Marble Wall Clading to Lift Loby
FAL-GF-01 False Ceiling
PANT-GF-02 Internal wall & ceiling painting
PANT-GF-03 Final internal painting
PANT-GF-04 Anticarbonation painting in wall
CARP-GF-01 Fixing of Door Frame
CARP-GF-02 Fixing of Door Shutter
CARP-GF-03 Fixing of Kitchen Cabinet
CARP-GF-04 Fixing of Wardrobes
MEP-GF-07 Sanitary fixing & Mixer
BLO-1F-01 Cleaning
BLO-1F-02 Block layout and checking
BLO-1F-04 Block work- 1F
BLO-1F-03 Internal Block Work
A0ON-1F-07 R.C.C Lintel
PLAS-1F-02 Celing Plaster- 1F
PLAS-1F-01 Wall Plaster - 1F
WPR-1F-02 Water proof coating to Wet areas
WPR-1F-03 Vertical side w/p of wet area
FL0-1F-10 Wet area -Ceramic Wall Clading
FL0-1F-04 Wet area- Ceramic flooring
FL0-1F-02 Floor Screed for Electrical Room
FL0-1F-01 Ceramic flooring inside room
FL0-1F-03 Ceramic tiling to balconey and terrase
FL0-1F-05 Ceramic tile to entrance loby
FL0-1F-06 Marble flooring to Corridor
FL0-1F-07 Skirting
FL0-1F-09 Corridor Wall Clading-Ceramic
FL0-1F-08 Telephone room & other room flooring
FL0-1F-11 Threshold
FAL-1F-01 1F-Baalcony False Ceiling
FAL-1F-02 False Ceiling
PANT-1F-01 Internal wall & ceiling painting
PANT-1F-02 Final internal painting
CARP-1F-01 Fixing of Door Frame
CARP-1F-02 Fixing of Door Shutter
CARP-1F-03 Fixing of Kitchen Cabinet
CARP-1F-04 Fixing of Wardrobes
MEP-1F-08 Bath Tub Fixing
MEP-1F-09 Sanitary fixing & Mixer
BLO-2F-01 clening
BLO-2F-02 Block layout and checking
BLO-2F-04 Block work- 2F
BLO-2F-03 Internal Block Work
A0ON-2F-07 R.C.C Lintel
PLAS-2F-01 Wall Plaster - 2F
PLAS-2F-02 Celing Plaster- 2F
WPR-2F-02 Water proof coating to Wet areas
WPR-2F-03 Vertical side w/p of wet area
FLO-2F-10 Wet area -Ceramic Wall Clading
FLO-2F-05 Wet area- Ceramic flooring
FLO-2F-01 Ceramic tile to entrance loby
FLO-2F-02 Floor Screed for Electrical Room
FLO-2F-03 Ceramic tile iside the room
FLO-2F-04 Ceramic tiling to balconey and terrase
FLO-2F-06 Marble flooring to Corridor
FLO-2F-07 Skirting
FLO-2F-09 Corridor Wall Clading-Ceramic
FLO-2F-08 Telephone room & other room flooring
FLO-2F-11 Threshold
FAL-2F-01 2F-Baalcony False Ceiling
FAL-2F-02 False Ceiling
PANT-2F-01 Internal wall & ceiling painting
PANT-2F-02 Final internal painting
CARP-2F-01 Fixing of Door Frame
CARP-2F-02 Fixing of Door Shutter
CARP-2F-03 Fixing of Kitchen Cabinet
CARP-2F-04 Fixing of Wardrobes
MEP-2F-08 Bath Tub Fixing
MEP-2F-09 Sanitary fixing & Mixer
BLO-3F-01 cleaning
BLO-3F-02 Block layout and checking
BLO-3F-03 Block work -3F
BLO-3F-04 Internal Block Work
A0ON-3F-07 R.C.C Lintel
PLAS-3F-01 Wall Plaster - 3F
PLAS-3F-02 Celing Plaster- 3F
WPR-3F-02 Water proof coating to Wet areas
WPR-3F-03 Vertical side w/p of wet area
FLO-3F-08 Wet area -Ceramic Wall Clading
FLO-3F-03 Wet area- Ceramic flooring
FLO-3F-01 Ceramic tiling to balconey and terrase
FLO-3F-02 Ceramic tile iside the room
FLO-3F-06 Floor Screed for Electrical Room
FLO-3F-04 Ceramic tile to entrance loby
FLO-3F-05 Skirting
FLO-3F-07 Telephone room & other room flooring
FLO-3F-09 Marble flooring to Corridor
FLO-3F-10 Threshold
FLO-3F-11 Corridor Wall Clading-Ceramic
FAL-3F-01 3F-Baalcony False Ceiling
FAL-3F-02 False Ceiling
PANT-3F-01 Internal wall & ceiling painting
PANT-3F-02 Final internal painting
CARP-3F-01 Fixing of Door Frame
CARP-3F-02 Fixing of Door Shutter
CARP-3F-03 Fixing of Kitchen Cabinet
CARP-3F-04 Fixing of Wardrobes
MEP-3F-08 Bath Tub Fixing
MEP-3F-09 Sanitary fixing & Mixer
BLO-4F-01 cleaning
BLO-4F-02 Block layout and checking
BLO-4F-04 Block work -4F
BLO-4F-03 Internal Block Work
A0ON-4F-07 R.C.C Lintel
PLAS-4F-01 Wall Plaster - 4F
PLAS-4F-02 Celing Plaster- 4F
WPR-4F-02 Water proof coating to Wet areas
WPR-4F-03 Vertical side w/p of wet area
FLO-4F-09 Wet area -Ceramic Wall Clading
FLO-4F-08 Wet area- Ceramic flooring
FLO-4F-02 Floor Screed for Electrical Room
FLO-4F-01 Ceramic tile to entrance loby
FLO-4F-03 Ceramic tiling to balconey and terrase
FLO-4F-05 Marble flooring to Corridor
FLO-4F-04 Ceramic tile iside the room
FLO-4F-10 Telephone room & other room flooring
FLO-4F-06 Corridor Wall Clading-Ceramic
FLO-4F-07 Skirting
FLO-4F-11 Threshold
FAL-4F-01 4F-Balcony False Ceiling
FAL-4F-02 False Ceiling
PANT-4F-01 Internal wall & ceiling painting
PANT-4F-02 Final internal painting
CARP-4F-02 Fixing of Door Frame
CARP-4F-03 Fixing of Door Shutter
CARP-4F-01 Fixing of Kitchen Cabinet
CARP-4F-04 Fixing of Wardrobes
MEP-4F-08 Bath Tub Fixing
MEP-4F-09 Sanitary fixing & Mixer
BLO-5F-01 cleaning
BLO-5F-02 Block layout and checking
BLO-5F-04 Block work -5F
BLO-5F-03 Internal Block Work
A0ON-5F-07 R.C.C Lintel
PLAS-5F-01 Wall Plaster - 5F
PLAS-5F-02 Celing Plaster- 5F
WRP-5F-02 Water proof coating to Wet areas
WRP-5F-03 Vertical side w/p of wet area
FLO-5F-10 Wet area -Ceramic Wall Clading
FLO-5F-04 Wet area- Ceramic flooring
FLO-5F-01 Floor Screed for Electrical Room
FLO-5F-03 Ceramic tile to entrance loby
FLO-5F-06 Marble flooring to Corridor
FLO-5F-05 Ceramic tile iside the room
FLO-5F-02 Ceramic tiling to balconey and terrase
FLO-5F-08 Telephone room & other room flooring
FLO-5F-07 Corridor Wall Clading-Ceramic
FLO-5F-09 Skirting
FLO-5F-11 Threshold
FAL-5F-01 5F-Balcony False Ceiling
FAL-5F-02 False Ceiling
PANT-5F-01 Internal wall & ceiling painting
PANT-5F-02 Final internal painting
CARP-5F-02 Fixing of Door Frame
CARP-5F-03 Fixing of Door Shutter
CARP-5F-01 Fixing of Kitchen Cabinet
CARP-5F-04 Fixing of Wardrobes
MEP-5F-08 Bath Tub Fixing
MEP-5F-09 Sanitary fixing & Mixer
BLO-6F-01 cleaning
BLO-6F-02 Block layout and checking
BLO-6F-03 Block work -6F
BLO-6F-04 Internal Block Work
A0ON-6F-07 R.C.C Lintel
PLAS-6F-01 Wall Plaster - 6F
PLAS-6F-02 Celing Plaster- 6F
WRP-6F-02 Water proof coating to Wet areas
WRP-6F-03 Vertical side w/p of wet area
FLO-6F-11 Wet area -Ceramic Wall Clading
FLO-6F-05 Wet area- Ceramic flooring
FLO-6F-01 Floor Screed for Electrical Room
FLO-6F-03 Ceramic tile to entrance loby
FLO-6F-04 Ceramic tile iside the room
FLO-6F-02 Ceramic tiling to balconey and terrase
FLO-6F-06 Skirting
FLO-6F-09 Marble flooring to Corridor
FLO-6F-10 Corridor Wall Clading-Ceramic
FLO-6F-07 Telephone room & other room flooring
FLO-6F-08 Threshold
FAL-6F-01 6F-Balcony False Ceiling
FAL-6F-02 False Ceiling
PANT-6F-01 Internal wall & ceiling painting
PANT-6F-02 Final internal painting
CARP-6F-01 Fixing of Door Frame
CARP-6F-02 Fixing of Door Shutter
CARP-6F-03 Fixing of Kitchen Cabinet
CARP-6F-04 Fixing of Wardrobes
MEP-6F-08 Bath Tub Fixing
MEP-6F-11 Sanitary fixing & Mixer
BLO-7F-01 cleaning
BLO-7F-02 Block layout and checking
BLO-7F-03 Block work -7F
BLO-7F-04 Internal Block Work
A0ON-7F-07 R.C.C Lintel
PLAS-7F-01 Wall Plaster - 7F
PLAS-7F-02 Celing Plaster- 7F
WRP-7F-02 Water proof coating to Wet areas
WRP-7F-03 Vertical side w/p of wet area
FLO-7F-11 Wet area -Ceramic Wall Clading
FLO-7F-06 Wet area- Ceramic flooring
FLO-7F-02 Floor Screed for Electrical Room
FLO-7F-01 Ceramic tile to entrance loby
FLO-7F-04 Skirting
FLO-7F-03 Ceramic tile iside the room
FLO-7F-05 Ceramic tiling to balconey and terrase
FLO-7F-08 Marble flooring to coridoor
FLO-7F-10 Corridor Wall Clading-Ceramic
FLO-7F-07 Telephone room & other room flooring
FLO-7F-09 Threshold
FAL-7F-01 7F-Balcony False Ceiling
FAL-7F-02 False Ceiling
PANT-7F-01 Internal wall & ceiling painting
PANT-7F-02 Final internal painting
CARP-7F-01 Fixing of Door Frame
CARP-7F-02 Fixing of Door Shutter
CARP-7F-03 Fixing of Kitchen Cabinet
CARP-7F-04 Fixing of Wardrobes
MEP-7F-08 Bath Tub Fixing
MEP-7F-12 Sanitary fixing & Mixer
BLO-HC-01 cleaning
BLO-HC-02 Block layout and checking
BLO-HC-04 Internal Block Work
BLO-HC-03 Block work -HC
A0ON-HC-10 R.C.C Lintel - HC
PLAS-HC-01 Wall Plaster - HC
A0AS-HC-02 Celing Plaster- HC
FLO-HC-07 rubber floor above screed in gym
FLO-HC-09 rubber skirting
FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)
FLO-HC-11 swimming pool wall clading
FLO-HC-14 Graniti Ceramic tile ( lift m/c room)
WRP-HC-02 Water proof coating to Wet areas
FLO-HC-02 White cement tiles
WRP-HC-03 Vertical side w/p of wet area
FLO-HC-04 wet area wall clading
FLO-HC-05 Ceramic flooring to swiming pool wall
A0LO-EX-02 Fixing of window sill
FLO-HC-01 Floor Screed for Electrical / store / tel room
FLO-HC-03 Marble flooring to lift loby
FLO-HC-06 Threshold
FLO-HC-08 Corridor Wall Clading-Ceramic
FLO-HC-12 Ceramic flooring to Filter Room
FLO-HC-13 Step to pool Deck
PANT-HC-01 Lift Int .wall bitumen coating
FAL-HC-01 False Ceiling
PANT-HC-02 Internal wall & ceiling painting
PANT-HC-03 Final internal painting
PANT-HC-04 Epoxy painting to staircase
CARP-HC-01 Fixing of Door Frame
CARP-HC-02 Fixing of Door shutter
MEP-HC-12 Sanitary fixing & Mixer
BLO-UR-01 Block work-UR
PLAS-UR-01 Wall Plaster- UR
PLAS-UR-02 Celing Plaster- UR
PLAS-UR-03 Staircase wall plaster
PLAS-UR-04 Staircase Ceilling plaster
CARP-UR-01 Fixing of Door Frame
CARP-UR-02 Fixing of Door shutter
MEP-B-02 MEP -Wall Conduites
MEP-B-03 Fixing of DB Back box ,GI box
MEP-B-04 Fixing of DB
MEP-B-06 Internal wiring
MEP-B-07 Main Cable work
MEP-B-08 Switches & Sockets
MEP-B-10 Instalation of Islolater for A/C
MEP-B-09 Light Fittings
MEP-GF-01 MEP -Wall Conduites
MEP-GF-02 Fixing of DB Back box ,GI box
MEP-GF-00 Fixing of DB
MEP-GF-04 Internal wiring
MEP-GF-06 Main Cable work
MEP-GF-08 Switches & Sockets
MEP-GF-10 Instalation of Islolater for A/C
MEP-GF-09 Light Fittings
MEP-1F-01 MEP -Wall Conduites
MEP-1F-04 Fixing of DB Back box ,GI box
MEP-1F-03 Fixing of DB
MEP-1F-05 Internal wiring
MEP-1F-07 Main Cable work
MEP-1F-10 Switches & Sockets
MEP-1F-12 Instalation of Islolater for A/C
MEP-1F-11 Light Fittings
MEP-2F-01 MEP -Wall Conduites
MEP-2F-02 Fixing of DB Back box ,GI box
MEP-2F-03 Fixing of DB
MEP-2F-05 Internal wiring
MEP-2F-07 Main Cable work
MEP-2F-10 Switches & Sockets
MEP-2F-12 Instalation of Islolater for A/C
MEP-2F-11 Light Fittings
MEP-3F-02 MEP -Wall Conduites
MEP-3F-04 Fixing of DB Back box ,GI box
MEP-3F-03 Fixing of DB
MEP-3F-05 Internal wiring
MEP-3F-07 Main Cable work
MEP-3F-10 Switches & Sockets
MEP-3F-12 Instalation of Islolater for A/C
MEP-3F-11 Light Fittings
MEP-4F-01 MEP -Wall Conduites
MEP-4F-04 Fixing of DB Back box ,GI box
MEP-4F-03 Fixing of DB
MEP-4F-05 Internal wiring
MEP-4F-07 Main Cable work
MEP-4F-10 Switches & Sockets
MEP-4F-15 Instalation of Islolater for A/C
MEP-4F-14 Light Fittings
MEP-5F-01 MEP -Wall Conduites
MEP-5F-04 Fixing of DB Back box ,GI box
MEP-5F-03 Fixing of DB
MEP-5F-05 Internal wiring
MEP-5F-07 Main Cable work
MEP-5F-13 Switches & Sockets
MEP-5F-15 Instalation of Islolater for A/C
MEP-5F-14 Light Fittings
MEP-6F-01 MEP -Wall Conduites
MEP-6F-03 Fixing of DB Back box ,GI box
MEP-6F-02 Fixing of DB
MEP-6F-06 Internal wiring
MEP-6F-07 Main Cable work
MEP-6F-13 Switches & Sockets
MEP-6F-15 Instalation of Islolater for A/C
MEP-6F-14 Light Fittings
MEP-7F-01 MEP -Wall Conduites
MEP-7F-03 Fixing of DB Back box ,GI box
MEP-7F-02 Fixing of DB
MEP-7F-05 Internal wiring
MEP-7F-07 Main Cable work
MEP-7F-13 Switches & Sockets
MEP-7F-14 Light Fittings
MEP-7F-15 Instalation of Islolater for A/C
MEP-HC-01 MEP -Wall Conduites
MEP-HC-02 Fixing of DB
MEP-HC-03 Fixing of DB Back box ,GI box
MEP-UR-01 MEP Wall Conduites & instalation of DB Box
MEP-HC-06 Internal wiring
MEP-HC-08 Main Cable work
MEP-HC-16 Switches & Sockets
MEP-HC-17 Light Fittings
MEP-HC-18 Instalation of Islolater for A/C
MEP-B-01 Water supply PEX piping
MEP-B-05 Water Supply PPR piping
MEP-GF-03 Water supply PEX piping
MEP-1F-02 Water supply PEX piping
MEP-GF-05 Water Supply PPR piping
MEP-2F-04 Water supply PEX piping
MEP-3F-01 Water supply PEX piping
MEP-1F-06 Water Supply PPR piping
MEP-2F-06 Water Supply PPR piping
MEP-4F-02 Water supply PEX piping
MEP-3F-06 Water Supply PPR piping
MEP-5F-02 Water supply PEX piping
MEP-4F-06 Water Supply PPR piping
MEP-6F-04 Water supply PEX piping
MEP-5F-06 Water Supply PPR piping
MEP-7F-04 Water supply PEX piping
MEP-6F-05 Water Supply PPR piping
MEP-HC-04 Water supply PEX piping
MEP-7F-06 Water Supply PPR piping
MEP-HC-05 Water Supply PPR piping
MEP-HC-07 Above ground Drainage
MEP-GF-11 Drainage Risers
MEP-GF-12 Water supply Riser
MEP-1F-13 Drainage Risers
MEP-1F-14 Water supply Riser
MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc
MEP-2F-13 Drainage Risers
MEP-2F-14 Water supply Riser
MEP-3F-13 Drainage Risers
MEP-3F-14 Water supply Riser
MEP-GF-13 Water Heater fixing
MEP-4F-11 Drainage Risers
MEP-4F-12 Water supply Riser
MEP-1F-15 Water Heater fixing
MEP-2F-15 Water Heater fixing
MEP-5F-10 Drainage Risers
MEP-5F-11 Water supply Riser
MEP-3F-15 Water Heater fixing
MEP-6F-09 Drainage Risers
MEP-6F-10 Water supply Riser
MEP-4F-13 Water Heater fixing
MEP-7F-09 Drainage Risers
MEP-7F-10 Water supply Riser
MEP-5F-12 Water Heter fixing
MEP-HC-09 Water supply Riser
MEP-HC-10 Drainage Risers
MEP-6F-12 Water Heater fixing
MEP-HC-13 Roof water supply work
MEP-7F-11 Water Heter fixing
MEP-HC-11 Water Heter fixing
MEP-HC-14 Water tank Instlation
MEP-HC-15 Pump Fitting
A0VAC-B-17 Ducting work for A/C
A0AC-GF-17 A/C unit hanging (indoor)
A0AC-1F-18 A/C unit hanging (indoor)
A0VAC-B-19 Ref. piping Work
A0AC-GF-18 Ducting work for A/C
A0AC-GF-20 Ref. piping Work
A0AC-2F-18 A/C unit hanging (indoor)
A0AC-3F-18 A/C unit hanging (indoor)
A0AC-1F-19 Ducting work for A/C
A0AC-1F-21 Ref. piping Work
A0AC-2F-19 Ducting work for A/C
A0AC-4F-18 A/C unit hanging (indoor)
A0AC-2F-21 Ref. piping Work
A0AC-GF-19 Ext.Fan Fixing
A0AC-GF-21 Air out let fixing
A0AC-3F-19 Ducting work for A/C
A0VAC-B-16 Fresh air Duct
A0AC-3F-21 Ref. piping Work
A0AC-5F-18 A/C unit hanging (indoor)
A0VAC-B-18 Ext.Fan Fixing
A0VAC-B-20 Air out let fixing
A0AC-4F-19 Ducting work for A/C
A0AC-4F-21 Ref. piping Work
A0AC-6F-18 A/C unit hanging (indoor)
A0AC-2F-20 Ext.Fan Fixing
A0AC-2F-22 Air out let fixing
A0AC-1F-20 Ext.Fan Fixing
A0AC-1F-22 Air out let fixing
A0AC-5F-19 Ducting work for A/C
A0AC-7F-18 A/C unit hanging (indoor)
A0AC-3F-20 Ext.Fan Fixing
A0AC-3F-22 Air out let fixing
A0AC-6F-19 Ducting work for A/C
A0AC-5F-21 Ref. piping Work
A0AC-6F-21 Ref. piping Work
A0AC-4F-20 Ext.Fan Fixing
A0AC-4F-22 Air out let fixing
A0AC-HC-20 A/C unit hanging (indoor)
A0AC-7F-19 Ducting work for A/C
A0AC-7F-21 Ref. piping Work
A0AC-HC-21 Ducting work for A/C
A0AC-5F-20 Ext.Fan Fixing
A0AC-5F-22 Air out let fixing
A0AC-6F-20 Ext.Fan Fixing
A0AC-6F-22 Air out let fixing
A0AC-HC-24 Ref. piping Work
A0AC-HC-23 Ext.Fan Fixing
A0AC-HC-25 Air out let fixing
A0AC-7F-20 Ext.Fan Fixing
A0AC-7F-22 Air out let fixing
A0AC-HC-22 A/C units ( outdoor)
WPR-1F-01 Balcony W/P 1F
PAV-01 Precast Wheel Stopper
WPR-2F-01 Balcony W/P 2F
WPR-3F-01 Balcony W/P 3F
WPR-4F-01 Balcony W/P 4F
WRP-5F-01 Balcony W/P 5F
WRP-6F-01 Balcony W/P 6F
PLAS-EX-01 External roof area Plastering
WRP-7F-01 Balcony W/P 7F
PANT-EX-01 Epoxy painting to Roof
PLAS-EX-02 Airwell Plastering
PANT-EX-02 Epoxy painting to side of stair wall to S.Pool
MET-06 Balconey Rainling
PANT-EX-03 Fless Coat to Air Wall
WRP-HC-01 waterproofing to swiming pool
WRP-EX-01 Roof , Parapet wall W/P & Testing
WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet
WRP-EX-03 Bitumen coating to External Block Wall -A
PLAS-EX-03 External elevation Plastering -A
FLO-EX-01 External elevation marble wall clading-A
MET-02 Aluminium Cladding On elevation- A
MET-04 Aluminium Claading Upper Roof Area
WRP-EX-04 Bitumen coating to External Block Wal- B
PLAS-EX-04 External elevation Plastering -B
FLO-EX-02 External elevation marble wall clading-B
MET-03 Aluminium Cladding On elevation- B
WRP-EX-05 Bitumen coating to External Block Wal-C
PLAS-EX-05 External elevation Plastering -C
FLO-EX-03 External elevation marble wall clading-C
MET-07 Aluminium Cladding On elevation- C
WRP-EX-06 Bitumen coating to External Block Wal-D
PLAS-EX-06 External elevation Plastering -D
FLO-EX-04 External elevation marble wall clading-D
MET-08 Aluminium Cladding On elevation- D
PAV-02 Fixing Kerb Stone at island & footh path
PAV-03 Fixing 60mm Paving block
PAV-04 80 mm Interlock at parking
PAV-05 Trafic line marking
A0MIS-03 Fixing of column guards
MET-05 Aluminium / door & Window
A0MIS-06 Compound Wall
MET-09 Staircase Hand Rail
MET-10 Cat ladders (For Airwel )
MET-11 Steel Pipe Gaurde (basement water side)
PR0-01 Security System
PR0-05 Gate barriers
PR0-03 Garbeg Disposal system
PR0-02 Pool Work
PRO-14 Reception counter
PR0-08 Instaltion Of Generator
PR0-09 TV system
PR0-06 Fixing of lockers
PR0-04 Sauna & Steam System
PR0-07 Lift instalation & Commissioning
PR0-11 Intercom system
PR0-10 Cradle system instalation
PR0-12 Transformar Instlation
PR0-13 Music system
TES-02 Testing & Commissioning
TES-01 Signage
TES-03 Civil Defance Inspection
TES-04 DM Inspection
TES-05 Complition certificate from DM
TES-06 P R O J E C T H A N D O V E R
SUCO-6F-15 Steel Work for 7.F Slab
SUCO-6F-16 MEP sleves & conduits for 7.F Slab
SUCO-6F-17 Seventh Floor Slab Casting (PART-B)
SUCO-6F-18 Deshuttering PART- B
SUCO-7F-01 steel work for column/A
SUCO-7F-02 Form work for column/A
SUCO-7F-03 Shear Wall /A
SUCO-7F-04 Column casting For RF /A Slab
SUCO-7F-05 Decking work for RF/A Slab
SUCO-7F-06 Steel Work for RF/A Slab
SUCO-7F-07 MEP sleves & conduits for RF/A Slab
SUCO-7F-08 Roof Floor Slab Casting[Part-A ]
SUCO-7F-09 Deshuttering PART- A
SUCO-7F-11 steel work for column
SUCO-7F-10 Shear Wall & Lift Core Wall
SUCO-7F-12 Form work for column
SUCO-7F-13 Column casting For RF Slab
SUCO-7F-14 Decking Work for R.F Slab
SUCO-7F-15 Steel Work for R.F Slab
SUCO-7F-16 MEP sleves & conduits for R.F Slab
SUCO-7F-17 Roof Slab Casting (PART-B)
SUCO-7F-18 Deshuttering PART- B
SUCO-HC-01 steel work for column
SUCO-HC-02 Shear Wall & Lift Core Wall
SUCO-HC-03 Form work for column
SUCO-HC-05 Parapet Wall
SUCO-HC-04 Column casting
SUCO-HC-07 Swimming pool Shell
SUCO-HC-10 Pool Deck
SUCO-HC-06 Decking Work for HC Slab
SUCO-HC-09 MEP sleves & conduits for HC Slab
SUCO-HC-08 Steel Work for HC Slab
SUCO-HC-11 Helth Club Slab Casting
SUCO-HC-12 Deshuttering
SUCO-UR-03 steel work for column
SUCO-UR-02 Shear Wall & Lift Core Wall
SUCO-UR-04 Form work for column
SUCO-UR-05 Parapet Wall above HC
SUCO-UR-01 Column casting For lift m/c room
SUCO-UR-06 Decking Work for lift m/c room
SUCO-UR-08 MEP sleves & conduits for lift m/c room
SUCO-UR-07 Steel Work for lift m/c room
SUCO-UR-09 Lift m/c room Slab
BLO-B-01 cleaning
BLO-B-02 Block layout and checking
BLO-B-03 Block work in Basement
BLO-B-04 R.C.C Lintel
PLAS-B-01 Wall Plaster - Basement
PLAS-B-02 Celing Plaster-Basement
FLO-B-02 marble flooring to lift loby
A0EXAV-09 Earth filling above raft 8’’tk
FLO-B-04 Marble Wall Clading to Lift Loby
FLO-B-05 4’’ PCC with mesh
FLO-B-07 Pump/ Store room flooring
FLO-B-01 Car parking /Driveway Floor Finishing
FLO-B-03 floor finish to water tank area
FLO-B-06 Wall clading to Pump room
FLO-B-08 Thrishold
FAL-B-01 False Ceiling
PANT-B-01 Internal wall & ceiling painting
PANT-B-02 Anticarbonation painting in wall
PANT-B-03 Final internal painting
CARP-B-01 Fixing of Door Frame
CARP-B-02 Fixing of Door Shutter
A0MIS-01 Substation Trenching Work
MET-01 Aluminium (LOUVER WORK) Substation
PANT-GF-01 Transformer room painting
A0PRO-17 Dewa Inspection Substation
A0PRO-18 Sub station hand over to DEWA
BLO-GF-01 cleaning
BLO-GF-02 Block layout and checking
BLO-GF-03 Internal Block Work
BLO-GF-04 Block work- GF
A0ON-GF-08 R.C.C Lintel
PLAS-GF-02 Celing Plaster- GF
PLAS-GF-01 Wall Plaster GF
WPR-GF-02 GF- Parking W/P
WPR-GF-01 Water proof coating to Wet areas
WPR-GF-03 Vertical side w/p of wet area
FLO-GF-08 Wet area wall clading ( garbage room)
FLO-GF-06 Wet area flooring (ceramic tiles)
WPR-GF-04 Water proofing to substation slab roof
FLO-GF-02 Floor Screed for Electrical Room/gym/
FLO-GF-01 4’’ PCC with mesh
FLO-GF-03 Floor Screed for M.hall
FLO-GF-05 Floor Screed for Electricaal Sub-station
FLO-GF-04 Car parking /Driveway Floor Finishing
FLO-GF-07 Floor Screed for Gym / Shop
FLO-GF-09 Mosaic flooring to stair floor & landing area
FLO-GF-10 Floor Screed for Gen. Room
FLO-GF-11 Store and other room flooring
FLO-GF-12 mosaic step
FLO-GF-14 Marble flooring to Entrance passage
FLO-GF-15 mosaic skirting for steps
FLO-GF-13 Threshold
FLO-GF-17 Fixing Marble Steps
FLO-GF-16 Marble Wall Clading to Lift Loby
FAL-GF-01 False Ceiling
PANT-GF-02 Internal wall & ceiling painting
PANT-GF-03 Final internal painting
PANT-GF-04 Anticarbonation painting in wall
CARP-GF-01 Fixing of Door Frame
CARP-GF-02 Fixing of Door Shutter
CARP-GF-03 Fixing of Kitchen Cabinet
CARP-GF-04 Fixing of Wardrobes
MEP-GF-07 Sanitary fixing & Mixer
BLO-1F-01 Cleaning
BLO-1F-02 Block layout and checking
BLO-1F-04 Block work- 1F
BLO-1F-03 Internal Block Work
A0ON-1F-07 R.C.C Lintel
PLAS-1F-02 Celing Plaster- 1F
PLAS-1F-01 Wall Plaster - 1F
WPR-1F-02 Water proof coating to Wet areas
WPR-1F-03 Vertical side w/p of wet area
FL0-1F-10 Wet area -Ceramic Wall Clading
FL0-1F-04 Wet area- Ceramic flooring
FL0-1F-02 Floor Screed for Electrical Room
FL0-1F-01 Ceramic flooring inside room
FL0-1F-03 Ceramic tiling to balconey and terrase
FL0-1F-05 Ceramic tile to entrance loby
FL0-1F-06 Marble flooring to Corridor
FL0-1F-07 Skirting
FL0-1F-09 Corridor Wall Clading-Ceramic
FL0-1F-08 Telephone room & other room flooring
FL0-1F-11 Threshold
FAL-1F-01 1F-Baalcony False Ceiling
FAL-1F-02 False Ceiling
PANT-1F-01 Internal wall & ceiling painting
PANT-1F-02 Final internal painting
CARP-1F-01 Fixing of Door Frame
CARP-1F-02 Fixing of Door Shutter
CARP-1F-03 Fixing of Kitchen Cabinet
CARP-1F-04 Fixing of Wardrobes
MEP-1F-08 Bath Tub Fixing
MEP-1F-09 Sanitary fixing & Mixer
BLO-2F-01 clening
BLO-2F-02 Block layout and checking
BLO-2F-04 Block work- 2F
BLO-2F-03 Internal Block Work
A0ON-2F-07 R.C.C Lintel
PLAS-2F-01 Wall Plaster - 2F
PLAS-2F-02 Celing Plaster- 2F
WPR-2F-02 Water proof coating to Wet areas
WPR-2F-03 Vertical side w/p of wet area
FLO-2F-10 Wet area -Ceramic Wall Clading
FLO-2F-05 Wet area- Ceramic flooring
FLO-2F-01 Ceramic tile to entrance loby
FLO-2F-02 Floor Screed for Electrical Room
FLO-2F-03 Ceramic tile iside the room
FLO-2F-04 Ceramic tiling to balconey and terrase
FLO-2F-06 Marble flooring to Corridor
FLO-2F-07 Skirting
FLO-2F-09 Corridor Wall Clading-Ceramic
FLO-2F-08 Telephone room & other room flooring
FLO-2F-11 Threshold
FAL-2F-01 2F-Baalcony False Ceiling
FAL-2F-02 False Ceiling
PANT-2F-01 Internal wall & ceiling painting
PANT-2F-02 Final internal painting
CARP-2F-01 Fixing of Door Frame
CARP-2F-02 Fixing of Door Shutter
CARP-2F-03 Fixing of Kitchen Cabinet
CARP-2F-04 Fixing of Wardrobes
MEP-2F-08 Bath Tub Fixing
MEP-2F-09 Sanitary fixing & Mixer
BLO-3F-01 cleaning
BLO-3F-02 Block layout and checking
BLO-3F-03 Block work -3F
BLO-3F-04 Internal Block Work
A0ON-3F-07 R.C.C Lintel
PLAS-3F-01 Wall Plaster - 3F
PLAS-3F-02 Celing Plaster- 3F
WPR-3F-02 Water proof coating to Wet areas
WPR-3F-03 Vertical side w/p of wet area
FLO-3F-08 Wet area -Ceramic Wall Clading
FLO-3F-03 Wet area- Ceramic flooring
FLO-3F-01 Ceramic tiling to balconey and terrase
FLO-3F-02 Ceramic tile iside the room
FLO-3F-06 Floor Screed for Electrical Room
FLO-3F-04 Ceramic tile to entrance loby
FLO-3F-05 Skirting
FLO-3F-07 Telephone room & other room flooring
FLO-3F-09 Marble flooring to Corridor
FLO-3F-10 Threshold
FLO-3F-11 Corridor Wall Clading-Ceramic
FAL-3F-01 3F-Baalcony False Ceiling
FAL-3F-02 False Ceiling
PANT-3F-01 Internal wall & ceiling painting
PANT-3F-02 Final internal painting
CARP-3F-01 Fixing of Door Frame
CARP-3F-02 Fixing of Door Shutter
CARP-3F-03 Fixing of Kitchen Cabinet
CARP-3F-04 Fixing of Wardrobes
MEP-3F-08 Bath Tub Fixing
MEP-3F-09 Sanitary fixing & Mixer
BLO-4F-01 cleaning
BLO-4F-02 Block layout and checking
BLO-4F-04 Block work -4F
BLO-4F-03 Internal Block Work
A0ON-4F-07 R.C.C Lintel
PLAS-4F-01 Wall Plaster - 4F
PLAS-4F-02 Celing Plaster- 4F
WPR-4F-02 Water proof coating to Wet areas
WPR-4F-03 Vertical side w/p of wet area
FLO-4F-09 Wet area -Ceramic Wall Clading
FLO-4F-08 Wet area- Ceramic flooring
FLO-4F-02 Floor Screed for Electrical Room
FLO-4F-01 Ceramic tile to entrance loby
FLO-4F-03 Ceramic tiling to balconey and terrase
FLO-4F-05 Marble flooring to Corridor
FLO-4F-04 Ceramic tile iside the room
FLO-4F-10 Telephone room & other room flooring
FLO-4F-06 Corridor Wall Clading-Ceramic
FLO-4F-07 Skirting
FLO-4F-11 Threshold
FAL-4F-01 4F-Balcony False Ceiling
FAL-4F-02 False Ceiling
PANT-4F-01 Internal wall & ceiling painting
PANT-4F-02 Final internal painting
CARP-4F-02 Fixing of Door Frame
CARP-4F-03 Fixing of Door Shutter
CARP-4F-01 Fixing of Kitchen Cabinet
CARP-4F-04 Fixing of Wardrobes
MEP-4F-08 Bath Tub Fixing
MEP-4F-09 Sanitary fixing & Mixer
BLO-5F-01 cleaning
BLO-5F-02 Block layout and checking
BLO-5F-04 Block work -5F
BLO-5F-03 Internal Block Work
A0ON-5F-07 R.C.C Lintel
PLAS-5F-01 Wall Plaster - 5F
PLAS-5F-02 Celing Plaster- 5F
WRP-5F-02 Water proof coating to Wet areas
WRP-5F-03 Vertical side w/p of wet area
FLO-5F-10 Wet area -Ceramic Wall Clading
FLO-5F-04 Wet area- Ceramic flooring
FLO-5F-01 Floor Screed for Electrical Room
FLO-5F-03 Ceramic tile to entrance loby
FLO-5F-06 Marble flooring to Corridor
FLO-5F-05 Ceramic tile iside the room
FLO-5F-02 Ceramic tiling to balconey and terrase
FLO-5F-08 Telephone room & other room flooring
FLO-5F-07 Corridor Wall Clading-Ceramic
FLO-5F-09 Skirting
FLO-5F-11 Threshold
FAL-5F-01 5F-Balcony False Ceiling
FAL-5F-02 False Ceiling
PANT-5F-01 Internal wall & ceiling painting
PANT-5F-02 Final internal painting
CARP-5F-02 Fixing of Door Frame
CARP-5F-03 Fixing of Door Shutter
CARP-5F-01 Fixing of Kitchen Cabinet
CARP-5F-04 Fixing of Wardrobes
MEP-5F-08 Bath Tub Fixing
MEP-5F-09 Sanitary fixing & Mixer
BLO-6F-01 cleaning
BLO-6F-02 Block layout and checking
BLO-6F-03 Block work -6F
BLO-6F-04 Internal Block Work
A0ON-6F-07 R.C.C Lintel
PLAS-6F-01 Wall Plaster - 6F
PLAS-6F-02 Celing Plaster- 6F
WRP-6F-02 Water proof coating to Wet areas
WRP-6F-03 Vertical side w/p of wet area
FLO-6F-11 Wet area -Ceramic Wall Clading
FLO-6F-05 Wet area- Ceramic flooring
FLO-6F-01 Floor Screed for Electrical Room
FLO-6F-03 Ceramic tile to entrance loby
FLO-6F-04 Ceramic tile iside the room
FLO-6F-02 Ceramic tiling to balconey and terrase
FLO-6F-06 Skirting
FLO-6F-09 Marble flooring to Corridor
FLO-6F-10 Corridor Wall Clading-Ceramic
FLO-6F-07 Telephone room & other room flooring
FLO-6F-08 Threshold
FAL-6F-01 6F-Balcony False Ceiling
FAL-6F-02 False Ceiling
PANT-6F-01 Internal wall & ceiling painting
PANT-6F-02 Final internal painting
CARP-6F-01 Fixing of Door Frame
CARP-6F-02 Fixing of Door Shutter
CARP-6F-03 Fixing of Kitchen Cabinet
CARP-6F-04 Fixing of Wardrobes
MEP-6F-08 Bath Tub Fixing
MEP-6F-11 Sanitary fixing & Mixer
BLO-7F-01 cleaning
BLO-7F-02 Block layout and checking
BLO-7F-03 Block work -7F
BLO-7F-04 Internal Block Work
A0ON-7F-07 R.C.C Lintel
PLAS-7F-01 Wall Plaster - 7F
PLAS-7F-02 Celing Plaster- 7F
WRP-7F-02 Water proof coating to Wet areas
WRP-7F-03 Vertical side w/p of wet area
FLO-7F-11 Wet area -Ceramic Wall Clading
FLO-7F-06 Wet area- Ceramic flooring
FLO-7F-02 Floor Screed for Electrical Room
FLO-7F-01 Ceramic tile to entrance loby
FLO-7F-04 Skirting
FLO-7F-03 Ceramic tile iside the room
FLO-7F-05 Ceramic tiling to balconey and terrase
FLO-7F-08 Marble flooring to coridoor
FLO-7F-10 Corridor Wall Clading-Ceramic
FLO-7F-07 Telephone room & other room flooring
FLO-7F-09 Threshold
FAL-7F-01 7F-Balcony False Ceiling
FAL-7F-02 False Ceiling
PANT-7F-01 Internal wall & ceiling painting
PANT-7F-02 Final internal painting
CARP-7F-01 Fixing of Door Frame
CARP-7F-02 Fixing of Door Shutter
CARP-7F-03 Fixing of Kitchen Cabinet
CARP-7F-04 Fixing of Wardrobes
MEP-7F-08 Bath Tub Fixing
MEP-7F-12 Sanitary fixing & Mixer
BLO-HC-01 cleaning
BLO-HC-02 Block layout and checking
BLO-HC-04 Internal Block Work
BLO-HC-03 Block work -HC
A0ON-HC-10 R.C.C Lintel - HC
PLAS-HC-01 Wall Plaster - HC
A0AS-HC-02 Celing Plaster- HC
FLO-HC-07 rubber floor above screed in gym
FLO-HC-09 rubber skirting
FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)
FLO-HC-11 swimming pool wall clading
FLO-HC-14 Graniti Ceramic tile ( lift m/c room)
WRP-HC-02 Water proof coating to Wet areas
FLO-HC-02 White cement tiles
WRP-HC-03 Vertical side w/p of wet area
FLO-HC-04 wet area wall clading
FLO-HC-05 Ceramic flooring to swiming pool wall
A0LO-EX-02 Fixing of window sill
FLO-HC-01 Floor Screed for Electrical / store / tel room
FLO-HC-03 Marble flooring to lift loby
FLO-HC-06 Threshold
FLO-HC-08 Corridor Wall Clading-Ceramic
FLO-HC-12 Ceramic flooring to Filter Room
FLO-HC-13 Step to pool Deck
PANT-HC-01 Lift Int .wall bitumen coating
FAL-HC-01 False Ceiling
PANT-HC-02 Internal wall & ceiling painting
PANT-HC-03 Final internal painting
PANT-HC-04 Epoxy painting to staircase
CARP-HC-01 Fixing of Door Frame
CARP-HC-02 Fixing of Door shutter
MEP-HC-12 Sanitary fixing & Mixer
BLO-UR-01 Block work-UR
PLAS-UR-01 Wall Plaster- UR
PLAS-UR-02 Celing Plaster- UR
PLAS-UR-03 Staircase wall plaster
PLAS-UR-04 Staircase Ceilling plaster
CARP-UR-01 Fixing of Door Frame
CARP-UR-02 Fixing of Door shutter
MEP-B-02 MEP -Wall Conduites
MEP-B-03 Fixing of DB Back box ,GI box
MEP-B-04 Fixing of DB
MEP-B-06 Internal wiring
MEP-B-07 Main Cable work
MEP-B-08 Switches & Sockets
MEP-B-10 Instalation of Islolater for A/C
MEP-B-09 Light Fittings
MEP-GF-01 MEP -Wall Conduites
MEP-GF-02 Fixing of DB Back box ,GI box
MEP-GF-00 Fixing of DB
MEP-GF-04 Internal wiring
MEP-GF-06 Main Cable work
MEP-GF-08 Switches & Sockets
MEP-GF-10 Instalation of Islolater for A/C
MEP-GF-09 Light Fittings
MEP-1F-01 MEP -Wall Conduites
MEP-1F-04 Fixing of DB Back box ,GI box
MEP-1F-03 Fixing of DB
MEP-1F-05 Internal wiring
MEP-1F-07 Main Cable work
MEP-1F-10 Switches & Sockets
MEP-1F-12 Instalation of Islolater for A/C
MEP-1F-11 Light Fittings
MEP-2F-01 MEP -Wall Conduites
MEP-2F-02 Fixing of DB Back box ,GI box
MEP-2F-03 Fixing of DB
MEP-2F-05 Internal wiring
MEP-2F-07 Main Cable work
MEP-2F-10 Switches & Sockets
MEP-2F-12 Instalation of Islolater for A/C
MEP-2F-11 Light Fittings
MEP-3F-02 MEP -Wall Conduites
MEP-3F-04 Fixing of DB Back box ,GI box
MEP-3F-03 Fixing of DB
MEP-3F-05 Internal wiring
MEP-3F-07 Main Cable work
MEP-3F-10 Switches & Sockets
MEP-3F-12 Instalation of Islolater for A/C
MEP-3F-11 Light Fittings
MEP-4F-01 MEP -Wall Conduites
MEP-4F-04 Fixing of DB Back box ,GI box
MEP-4F-03 Fixing of DB
MEP-4F-05 Internal wiring
MEP-4F-07 Main Cable work
MEP-4F-10 Switches & Sockets
MEP-4F-15 Instalation of Islolater for A/C
MEP-4F-14 Light Fittings
MEP-5F-01 MEP -Wall Conduites
MEP-5F-04 Fixing of DB Back box ,GI box
MEP-5F-03 Fixing of DB
MEP-5F-05 Internal wiring
MEP-5F-07 Main Cable work
MEP-5F-13 Switches & Sockets
MEP-5F-15 Instalation of Islolater for A/C
MEP-5F-14 Light Fittings
MEP-6F-01 MEP -Wall Conduites
MEP-6F-03 Fixing of DB Back box ,GI box
MEP-6F-02 Fixing of DB
MEP-6F-06 Internal wiring
MEP-6F-07 Main Cable work
MEP-6F-13 Switches & Sockets
MEP-6F-15 Instalation of Islolater for A/C
MEP-6F-14 Light Fittings
MEP-7F-01 MEP -Wall Conduites
MEP-7F-03 Fixing of DB Back box ,GI box
MEP-7F-02 Fixing of DB
MEP-7F-05 Internal wiring
MEP-7F-07 Main Cable work
MEP-7F-13 Switches & Sockets
MEP-7F-14 Light Fittings
MEP-7F-15 Instalation of Islolater for A/C
MEP-HC-01 MEP -Wall Conduites
MEP-HC-02 Fixing of DB
MEP-HC-03 Fixing of DB Back box ,GI box
MEP-UR-01 MEP Wall Conduites & instalation of DB Box
MEP-HC-06 Internal wiring
MEP-HC-08 Main Cable work
MEP-HC-16 Switches & Sockets
MEP-HC-17 Light Fittings
MEP-HC-18 Instalation of Islolater for A/C
MEP-B-01 Water supply PEX piping
MEP-B-05 Water Supply PPR piping
MEP-GF-03 Water supply PEX piping
MEP-1F-02 Water supply PEX piping
MEP-GF-05 Water Supply PPR piping
MEP-2F-04 Water supply PEX piping
MEP-3F-01 Water supply PEX piping
MEP-1F-06 Water Supply PPR piping
MEP-2F-06 Water Supply PPR piping
MEP-4F-02 Water supply PEX piping
MEP-3F-06 Water Supply PPR piping
MEP-5F-02 Water supply PEX piping
MEP-4F-06 Water Supply PPR piping
MEP-6F-04 Water supply PEX piping
MEP-5F-06 Water Supply PPR piping
MEP-7F-04 Water supply PEX piping
MEP-6F-05 Water Supply PPR piping
MEP-HC-04 Water supply PEX piping
MEP-7F-06 Water Supply PPR piping
MEP-HC-05 Water Supply PPR piping
MEP-HC-07 Above ground Drainage
MEP-GF-11 Drainage Risers
MEP-GF-12 Water supply Riser
MEP-1F-13 Drainage Risers
MEP-1F-14 Water supply Riser
MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc
MEP-2F-13 Drainage Risers
MEP-2F-14 Water supply Riser
MEP-3F-13 Drainage Risers
MEP-3F-14 Water supply Riser
MEP-GF-13 Water Heater fixing
MEP-4F-11 Drainage Risers
MEP-4F-12 Water supply Riser
MEP-1F-15 Water Heater fixing
MEP-2F-15 Water Heater fixing
MEP-5F-10 Drainage Risers
MEP-5F-11 Water supply Riser
MEP-3F-15 Water Heater fixing
MEP-6F-09 Drainage Risers
MEP-6F-10 Water supply Riser
MEP-4F-13 Water Heater fixing
MEP-7F-09 Drainage Risers
MEP-7F-10 Water supply Riser
MEP-5F-12 Water Heter fixing
MEP-HC-09 Water supply Riser
MEP-HC-10 Drainage Risers
MEP-6F-12 Water Heater fixing
MEP-HC-13 Roof water supply work
MEP-7F-11 Water Heter fixing
MEP-HC-11 Water Heter fixing
MEP-HC-14 Water tank Instlation
MEP-HC-15 Pump Fitting
A0VAC-B-17 Ducting work for A/C
A0AC-GF-17 A/C unit hanging (indoor)
A0AC-1F-18 A/C unit hanging (indoor)
A0VAC-B-19 Ref. piping Work
A0AC-GF-18 Ducting work for A/C
A0AC-GF-20 Ref. piping Work
A0AC-2F-18 A/C unit hanging (indoor)
A0AC-3F-18 A/C unit hanging (indoor)
A0AC-1F-19 Ducting work for A/C
A0AC-1F-21 Ref. piping Work
A0AC-2F-19 Ducting work for A/C
A0AC-4F-18 A/C unit hanging (indoor)
A0AC-2F-21 Ref. piping Work
A0AC-GF-19 Ext.Fan Fixing
A0AC-GF-21 Air out let fixing
A0AC-3F-19 Ducting work for A/C
A0VAC-B-16 Fresh air Duct
A0AC-3F-21 Ref. piping Work
A0AC-5F-18 A/C unit hanging (indoor)
A0VAC-B-18 Ext.Fan Fixing
A0VAC-B-20 Air out let fixing
A0AC-4F-19 Ducting work for A/C
A0AC-4F-21 Ref. piping Work
A0AC-6F-18 A/C unit hanging (indoor)
A0AC-2F-20 Ext.Fan Fixing
A0AC-2F-22 Air out let fixing
A0AC-1F-20 Ext.Fan Fixing
A0AC-1F-22 Air out let fixing
A0AC-5F-19 Ducting work for A/C
A0AC-7F-18 A/C unit hanging (indoor)
A0AC-3F-20 Ext.Fan Fixing
A0AC-3F-22 Air out let fixing
A0AC-6F-19 Ducting work for A/C
A0AC-5F-21 Ref. piping Work
A0AC-6F-21 Ref. piping Work
A0AC-4F-20 Ext.Fan Fixing
A0AC-4F-22 Air out let fixing
A0AC-HC-20 A/C unit hanging (indoor)
A0AC-7F-19 Ducting work for A/C
A0AC-7F-21 Ref. piping Work
A0AC-HC-21 Ducting work for A/C
A0AC-5F-20 Ext.Fan Fixing
A0AC-5F-22 Air out let fixing
A0AC-6F-20 Ext.Fan Fixing
A0AC-6F-22 Air out let fixing
A0AC-HC-24 Ref. piping Work
A0AC-HC-23 Ext.Fan Fixing
A0AC-HC-25 Air out let fixing
A0AC-7F-20 Ext.Fan Fixing
A0AC-7F-22 Air out let fixing
A0AC-HC-22 A/C units ( outdoor)
WPR-1F-01 Balcony W/P 1F
PAV-01 Precast Wheel Stopper
WPR-2F-01 Balcony W/P 2F
WPR-3F-01 Balcony W/P 3F
WPR-4F-01 Balcony W/P 4F
WRP-5F-01 Balcony W/P 5F
WRP-6F-01 Balcony W/P 6F
PLAS-EX-01 External roof area Plastering
WRP-7F-01 Balcony W/P 7F
PANT-EX-01 Epoxy painting to Roof
PLAS-EX-02 Airwell Plastering
PANT-EX-02 Epoxy painting to side of stair wall to S.Pool
MET-06 Balconey Rainling
PANT-EX-03 Fless Coat to Air Wall
WRP-HC-01 waterproofing to swiming pool
WRP-EX-01 Roof , Parapet wall W/P & Testing
WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet
WRP-EX-03 Bitumen coating to External Block Wall -A
PLAS-EX-03 External elevation Plastering -A
FLO-EX-01 External elevation marble wall clading-A
MET-02 Aluminium Cladding On elevation- A
MET-04 Aluminium Claading Upper Roof Area
WRP-EX-04 Bitumen coating to External Block Wal- B
PLAS-EX-04 External elevation Plastering -B
FLO-EX-02 External elevation marble wall clading-B
MET-03 Aluminium Cladding On elevation- B
WRP-EX-05 Bitumen coating to External Block Wal-C
PLAS-EX-05 External elevation Plastering -C
FLO-EX-03 External elevation marble wall clading-C
MET-07 Aluminium Cladding On elevation- C
WRP-EX-06 Bitumen coating to External Block Wal-D
PLAS-EX-06 External elevation Plastering -D
FLO-EX-04 External elevation marble wall clading-D
MET-08 Aluminium Cladding On elevation- D
PAV-02 Fixing Kerb Stone at island & footh path
PAV-03 Fixing 60mm Paving block
PAV-04 80 mm Interlock at parking
PAV-05 Trafic line marking
A0MIS-03 Fixing of column guards
MET-05 Aluminium / door & Window
A0MIS-06 Compound Wall
MET-09 Staircase Hand Rail
MET-10 Cat ladders (For Airwel )
MET-11 Steel Pipe Gaurde (basement water side)
PR0-01 Security System
PR0-05 Gate barriers
PR0-03 Garbeg Disposal system
PR0-02 Pool Work
PRO-14 Reception counter
PR0-08 Instaltion Of Generator
PR0-09 TV system
PR0-06 Fixing of lockers
PR0-04 Sauna & Steam System
PR0-07 Lift instalation & Commissioning
PR0-11 Intercom system
PR0-10 Cradle system instalation
PR0-12 Transformar Instlation
PR0-13 Music system
TES-02 Testing & Commissioning
TES-01 Signage
TES-03 Civil Defance Inspection
TES-04 DM Inspection
TES-05 Complition certificate from DM
TES-06 P R O J E C T H A N D O V E R
hussein obey
User offline. Last seen 13 years 5 weeks ago. Offline
Joined: 22 Jun 2005
Posts: 30
Hi all,
Hi Mr Khaled
Hi Mr Sukumaran Subaramaniyan

I intend to set some kind of rewarding system as a motivation for our selves to work on this project.
So, I need to formulate an evaluation committee to evaluate posts then based on the committee evaluation the Planner will win the reward for each approved post.

-----------
The Reward:
-----------
All participants that their posts are approved by the committee will win a valuable Project Management Book and have the right to select one of the following books:
- McGraw Hill - Project Management
- Mcgraw-Hill The Six Sigma Project Planner Ebook
- AMACON - Modern Project Management
- Project Management - New Six Sigma - A Leader Guide To Achieving Rapid Business (Prentice Hall)
- Project Management - The Evolutionary Project Manager’s Handbook
- Project Management - The Project Manager’s MBA
- Project Management Manual
- Project Management Skills
- Project Manager Manual
- Wiley - Practical Project Management
- Wiley - Project Management Methodologies

So, Mr Khaled,Mr Sukumaran Subaramaniyan I invite you to be the first two members of the A/M committee so, please if you agree let me know.

All members can begin posts submition and receiving rewards from now. temporarily I will evaluate the posts till the committee is founded and any one of the members is encouraged to sent his evaluation to any post.

Thank You all,

Hussein Abdel Maksoud, M.Sc. construction Management
hamaksoud@yahoo.com
Khaled Bashiti
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 2 Nov 2001
Posts: 18
Groups: None
Hi Hussein,

As a begining stop dividing the subject and copying it to another Posts. i understand that u want to differentiate between different trades but this will not help.

What really help is that u atleast start with one trade then once its finished u can start the other ones, where u will find that 60% of information for the next trade was discussed, because trades sequence is like a net.

So just start with one trade if i m not mistaken Start with Construction and leave the Pre-Construction(MasterPlan, Design & Engineering,Tendering)to a later stage.

as u have categorized yr Method Statement lets start on:

1- List of activities including prerequisits.

Civil & Infrastructure Works for Terrestrial(Marine Works will Need another Category):

- Mobilization
- Enabling Works
- Enviromental Remediation Works
- Land Reclamination & Mass Grading
- Infrastructure Works
- Building Structure
(Lets Start listing activities for the above ones, as u know they can be built from a huge number of activities, this was a start-up)

as for the hereunder catergories lets add ther comments also.

2- Activity Sequence (either mandatory or discretionary).
3- Resources required (including material, labor, equipment).
4- Factors to be considered for duration estimation.
5- Lags or leads that may be required.
6- Risk factors in metrics of cost and time impact.


Its a huge job it need patient and time, but its a startup.

regards,

hussein obey
User offline. Last seen 13 years 5 weeks ago. Offline
Joined: 22 Jun 2005
Posts: 30
Dear Mr. Khaled Bashiti, Dear All,

Thank you very much on your response in our brainstorming.

1. You are right, the subject needs to be more simplified and clear with definite form and deliverables and I am working on that.

2. The WBS I suggested depended on the Idea of standardization not on specific type of structure, location,.... the output we hope to get out of this brainstorming is a categorized list of all workpackages that a planning engineer may face in any project with the method of construction of each. When the planner works on a real world project he will select only packages included in his project and put them in the appropriate location in his project WBS.

If we considered your example:

1. The realworld project will be an Hotel with the following potion of a WBS:

+ Hotel Project
+ Basement
....
+ Ground floor
....
+ Firtst floor
+ Main Corridor,Lift Looby,Room Enterance
....
+ Rooms
....
+ Toilets
- MEP works
- Finishes
- Fit-outs
- Furnitures
+ Service Rooms
....

2. Deliverables in our project will be organized in a standardized fashion not in a projectized fashion to include all possible types of work under each category (Uniformat) as shown totally in my topic "Methods of Construction" on this forum.

for example: the Planner in the realworld project (the above shown WBS) needs the MEP, Finishes, Fit-outs and Furnitures not only once but several times according to instances of occurance on the project but he will find each one in only one location in out "project for standardization" he will find:

- MEP in Item D of the Uniformat (shown in my topic "Methods of Construction")

- Equipment in Item E of the Uniformat (shown in my topic "Methods of Construction")

- Finishes and fit-outs in Item C of the Uniformat (shown in my topic "Methods of Construction")

and so on.

3. The planner takes all his packages and palce them where ever needed in his realworld project.

-----------------------------------------------------------

The question now is "What do we mean exactly with Method of construction?"

Well, The initial meaning I suggest to start with is (According to PMI-PMBOK 2000):
- List of activities including prerequisits.
- Activity Sequence (either mandatory or discretionary).
- Resources required (including material, labor, equipment).
- Factors to be considered for duration estimation.
- Lags or leads that may be required.
- Risk factors in metrics of cost and time impact.

Mr. Khaled Thanks a lot and I hope to receive more of your responses and ideas to help in completing this project.

Thank you All,

Hussein Abdel Maksoud, MSc Construction Management.
hamaksoud@yahoo.com
Khaled Bashiti
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 2 Nov 2001
Posts: 18
Groups: None
Hi Hussein,

unfortunetly the way u r presenting the issue confuse the viewers, if u want to do a method statement for Interior works or for Furniture or MEP or Structure you can’t just come and list Codes.

Simply say i need to get information concerning this subject whats the best way to deal with.

Answers will fly over from all memebers.

to push members to participate u should guide them with a startup

Example:

Method statement for Interiors u have to differntiate between Finishes, Fit-outs & Furnitures & Equipments.

Usually what can we say is the best way to proceed with work in a Hotel(specify the project because u have a large scale of jobs)even which part of a Hotel Typical Floors

how u will do the Works simply we will break Each Level of the Typical Floors into Zones(1- Main Corridor, Lift Looby, & Room Enterance all Togather. 2- Rooms. 3- Toilets. 4- Service Rooms) this break down it depends upon the included trades means: each zone have its own MEP works also Finishes, Fit-outs, & Furnitures automatically the crews can be divided into those zones.

So We have to Specify the 1- Project Type 2- Trade 3- Zone
4- Gangs Flow

Depending at Project type each one can put his input, also according to Trade.

hope that i have helped without any misunderstanding.