Hi,
I have an activity which started earlier than forecasted and will consequently finish earlier.
The problem is when I put the expected finish date on Feb 15th I can't draw the finish date earlier than Feb 22nd.
I get the message : "Finish date can not be earlier than remain finish date"
Somebody know how to solve this ?
Thanks
Jean
Thanks guys for your help !
Jean
Do not overlook Gary second point.
Remaining duration start depend on the out-of-sequence setting. There are several settings; such as progress override and retained logic among the most common, P6 I understand provides another and recently I learned of a % rule. All applied across the board, none a sure bet. I agree with the recommended practice of using retained logic but will add always correct logic even when your choice seems like in agreement, if latter on you change options it will no longer be in agreement, on a claim the faulty logic might be questioned as well as any late fix.
Take a look at the following image.
If you setup EF to be day 26 the Overridden option will calculate RD=18 days. The second option will calculate and change RD to 6 days without any warning if you fix EF.
Under resource leveling this is somewhat more complicated and P6 introduced what they call Remaining Float dependent on resource availability but not necessarily equal to resource constrained float judging from unreliable float computations by P6 observed by many as reported in several Planning Planet threads.
Ron Winter provided us with an excellent reference for P6 Dates you shall take a look. A reference I never get tired of posting as I find it so good.
http://www.ronwinterconsulting.com/Understanding_P6_Dates.pdf
Jean:
1) If it started earlier than forecast, does that mean all of it's predecessor requirements for starting had not been met? If so, you have Out Of Sequence (OOS) working -ammend the predecessor logic to reflect what has actually happened.
This will probably fix your issue with expected finish, but please note:
2) Best practise is not to use expected finish dates. -Better to adjust remaining duration instead.
Cheers,
G