Changing Activity type for 3000+ Activities

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

U
usman arshad 👤 Member for 15 years 5 months

John

1- u can do it through global change

2-u can add one column for Activity type and then change one activity type manually and crtl select other acitivites and press crt+E. this is like in excel we have crtl+d option.