David Ball
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 26 Jan 2012
Posts: 10
Groups: None

Hi Planners,

When I update my master schedule by importing an updated XER file (provided by a contractor) the Resources assigned to activities are duplicated.

What causes this and how can I import the XER file without duplicating Resources?

 

Thanks very much

DFB

Replies

Anning Sofi
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

To solve this problem,

1) Go to Projects Screen, (the view that displays all the Projects)

2) at the bottom tabs of the Project view, look for the Resources Tab.

3) Under the resource tab, look for the Resource Assignments (bold) letters

4). Untick or uncheck the box that says "Resources can be assigned to the same activity more than once."

Done

Raymund de Laza
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi David,

The imported schedule might carry a resource with the same resource name but different resource ID or vice versa.

Extra Spaces in the Resource ID or Resource name will contribute to the problem.

David Ball
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 26 Jan 2012
Posts: 10
Groups: None

Hi Raymond,

 

Thanks for the tip, but I am pretty sure the import settings are fine. I have been using the same Project Update Options without a problem for a while now. But with this new schedule I get duplicte resources.

 

DFB

Raymund de Laza
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

When importing.. choose update Project then modify the Project Update Options accordingly.

 