Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Same value of Budget Labor Units and Custom Defined Field using global change in P6

6 replies [Last post]
Num Lock
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Dear All,

Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around? 

Thank you.

Regards,

Num

Replies

Num Lock
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, anyone has solution for this one? Thanks.

Num Lock
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, anyone has solution for this one? Thanks.

Num Lock
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, I simply use 2 global change:

1. Global change 1 (Activities):

user_number6 = _sc wf

2. Global change 2 (Activity Resource Assignment):

Budgeted labor units = user_number6

Num Lock
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi I already changed the security profiles but still it doesn't work.

Amit Parmar (PMP)
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

Can you please tell me what formula are you using while using global change.

Regards

Amit Parmar

Check out my blog on PrimaveraBlog at http://www.primaverablog.in

Raymund de Laza
User offline. Last seen 1 week 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi Num Lock,

Please check your Security Profile assigned to you if you are not a superuser. You might not allowed to edit part or whole of the project data.

 

Hope this will help.

 

Regards,

 

Raymund