Early Curve "Cost" & Late Curve "Cost"

1 reply [Last post]
Jojie Pepito
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 15
Guys, I need your help...im preparing a work program as per P6 cost loaded schedule. My problem are the following;

1. How can i track the early cost values?
2. How can i track the late cost values?

Help please...

Jp

Replies

Rodel Marasigan
User offline. Last seen 1 day 3 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jojie,
Click Below where I uploaded at Snips on how to create Remaining Late spreadsheet Value and histogram. It may help
Remaining Late Spreadsheet & Histogram