Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to create Cumulative Late Curve in P6

129 replies [Last post]
Paul Yoon
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 28 Aug 2004
Posts: 8
Groups: TILOS
I am trying to find out how to generate a cumulative Late Curve and cumulative early curve for my cost loading/cash flow in P6. However I still don’t know how to do it.

In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???

Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

there is no link just go to view show on bottom resource usage profile and select either the early or late dates

view show on bottom resource usage profile then select 

remaining early and or remaining late

RAJEEV KUMAR
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 14 Jan 2018
Posts: 2
Groups: None

Hi , Please send me the steps for creating  late curve and early curve. Thanks, Rajeev

SAIDA NJIM
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 24 May 2012
Posts: 7
Groups: None

Hi Arnold

 

Please send this document in my mail : fcs.btp@topnet.tn

 

Thank you very much

Mohammed Siraj
User offline. Last seen 9 years 45 weeks ago. Offline
Joined: 27 Apr 2008
Posts: 3
Groups: None

Hi Arnold,

Please share with me the steps.

My email is siraj2000@sify.com

Regards,

Siraj

Karim Ragab
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 6 Dec 2011
Posts: 7

Hi Arnold,

Please, also send me the steps on how to create the comulative late curve in P6.
This is my email :  karimrgb@hotmail.com

Thanks & Regards

karim

Khaja Sharief
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

Early & late curves can be generated straight away once you have resources loaded schedule in P6.

You can find these curves ready made for you in activity usage profile window.  Right click on the graph and select At activity usage profile options. Under Bar/curves, select Remaining Early or Remaining late curve.

Cheers...

Arshad Jamil
User offline. Last seen 11 years 23 weeks ago. Offline
Joined: 3 Jul 2003
Posts: 6

Hi Arnold,

Please, also send me the steps on how to create the comulative late curve in P6.
This is my email :          jamil_arshad@rediffmail.com

Thanks & Regards

jamil

Sunil Babu
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Arnold,

pls send me also..(s -curve late and early)

mail: sb_sunil2000@yahoo.com

Thanks in advance

Sunil.

tariq amine
User offline. Last seen 11 years 43 weeks ago. Offline
Joined: 1 Oct 2010
Posts: 2

hi, I'm new in this forum & I ask you to teach me how to create a s-urve conjugated with global change ??? thank you.

dwi jaka prastya
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 21 Apr 2012
Posts: 11
Groups: None

Hi Mr Arnold

can you send me also

prastya.dj@gmail.com

Thanks

Badrul Helmi
User offline. Last seen 11 years 47 weeks ago. Offline
Joined: 16 Mar 2012
Posts: 2
Groups: None

Arnold, send to me too..

bentonitecement@yahoo.com.my

 

tqvm

Rafael Davila
User offline. Last seen 10 hours 1 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

I do not use P6 but using Google found the following link that shows a way to generate the data for Excel, then with a knowledge of Excel or using an Excel template you can generate the combined curves.

http://primaverarena.com/wp-content/uploads/2010/05/S-curve-creation-for-P6.pdf

The following links provides some tutorials that might be of interest and perhaps showing a different approach.

http://www.toolboxforplanning.com/p/tutorials.html

http://www.toolboxforplanning.com/2010/10/excel-2003-tutorial-creating-progress-s_16.html

You can download their template or a modified version I just created to include early and late banana curves from the following link.

http://www.mediafire.com/download.php?ekc33bya2nd44e4 

Photobucket

I prefer to display on the vertical axis the absolute values instead of percentages as it can create confusion when contract value changes.

Because of the way P6 stores period performance on uncompleted activities there can be discrepancies on displayed period performance if you do not make use of financial periods. The following link can provide you with an introduction on this issue.

http://primaverablog.in/2011/03/financial-periods-2/

Hope this help.

Regards,

Rafael

Ashraf El Sharkawi
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 21 May 2012
Posts: 3
Groups: None

can you please send me the steps and the required software( or plugin) to be able to generate these curves?

ashraf_shoukry_5@hotmail.com

Ashraf El Sharkawi
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 21 May 2012
Posts: 3
Groups: None

can you please send me the steps and the required software( or plugin) to be able to generate these curves?

ashraf_shoukry_5@hotmail.com

Imran Rana
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 27 Feb 2011
Posts: 6

can u send me to rana.imran@hotmail.com

Hey Guys,

Could please send me the procedure?Thanks!email: j.maliwat@yahoo.com

J Martin
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 30 Jan 2007
Posts: 2
Groups: None

Arnold will you please send me the steps? wonjmartin@hotmail.com

Thank you

Christian Chandler
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 5
Groups: None

Hi Arnold,

 

Would you please send me the details also; christian.chandler@riotinto.com.

 

Cheers

Christian
Christian Chandler
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 5
Groups: None

Hi Arnold,

 

Would you please send me the details also; christian.chandler@riotinto.com.

 

Cheers

German Rogers
User offline. Last seen 8 years 41 weeks ago. Offline
Joined: 29 Dec 2011
Posts: 2
Groups: None

Hi Arnold, may I request you a copy of the instructions about how to create the cumulative curve?

I will be thankful.

My email address is:  germanrogers@gmail.com

Thanks,

German.

 

Angelito Estrella
User offline. Last seen 1 year 3 weeks ago. Offline

good day arnold,

this may a bit late

still, please could you send me the steps

iam new in p6

appreciate your help

my eadd; amestrella25@yahoo.com

ali ahmad
User offline. Last seen 12 years 17 weeks ago. Offline
Joined: 2 Dec 2011
Posts: 2
Groups: None

me too, really need it   cat56456@yahoo.com

Ayman Eleish
User offline. Last seen 12 years 4 weeks ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Dear All,

That can be done from the Assignment screen to copy the resorces usage and to paste in excel sheet.

Regards,

inas atef
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 13 Dec 2011
Posts: 2
Groups: None

hi

can u send me also
 stars.light@live.com

 

best regards.

John Rovir Ferna...
User offline. Last seen 9 years 45 weeks ago. Offline
Joined: 21 Apr 2011
Posts: 5
Groups: None

Hi Arnold,

 

Can you kindly send it to me as well. please.  jrrfernandez@yahoo.com

Thank you.

 

JRF

Rafael Davila
User offline. Last seen 10 hours 1 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Just remember you will need two sets of early and late S curves (two banana curves). One for the baseline schedule and another for the current schedule that shall not only display actual performance up to data date but also shall display projected early and late S curves after data date.

S Curves

Also remember to apply postings to financial periods if your software is not capable of display correct values without using periods, an unneeded patch in more capable software. At least P6 is better than SureTrak that was not able to display correct values and did not provided such patch. P6 requires such patch same as P3 but at least P6 allows you to edit closed periods while P3 does not. The BUG has to do with the design of the mathematical distribution of activities that span performance over two updating periods, for most people the way around using financial periods is ok.

Irfan Khan
User offline. Last seen 10 weeks 4 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

pls send me here irfan_kn2006@hotmil.com

 

i will be thankful ..........

 

 

 

John Jacob
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 30 Jul 2007
Posts: 6
Groups: None

Hi Arnold,

 

Admit I am very late in tihis forum. But much appreciate if you could send me the late and early curve generation techniques.

My email is jjacobjp@yahoo.com

Many Thanks.

John.

John Jacob
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 30 Jul 2007
Posts: 6
Groups: None

Hi Arnold,

 

Admit I am very late in this forum. But much appreciate if you could send me the late and early curve generation techniques.

My email is jjacobjp@yahoo.com

Many Thanks.

John.

dulat Praliyev
User offline. Last seen 4 years 12 weeks ago. Offline
Joined: 18 Apr 2011
Posts: 9
Groups: None

Hey all

 

Can you send detial as well??

Shalabh Gupta
User offline. Last seen 13 years 6 days ago. Offline
Joined: 4 Dec 2007
Posts: 5
Groups: None

Hey All

 

i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

PERCENTAGE PHYSICAL PROGRESS CALCULATION?

Shalabh Gupta
User offline. Last seen 13 years 6 days ago. Offline
Joined: 4 Dec 2007
Posts: 5
Groups: None

Hey All

 

i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

PERCENTAGE PHYSICAL PROGRESS CALCULATION?

Shalabh Gupta
User offline. Last seen 13 years 6 days ago. Offline
Joined: 4 Dec 2007
Posts: 5
Groups: None

Hey All

 

i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

PERCENTAGE PHYSICAL PROGRESS CALCULATION?

Mohamed Fawzy
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 5
Groups: None

hey

can you send me the steps for doing the early and the late cumaltive curves on P6,please send it to my email

lost_enigma666@hotmail.com    thanks

Mohamed Fawzy
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 5
Groups: None

hey can you send me the steps of how i do the early and late cumaltive cash flow for cost and time for the whole project, please send me the steps at    lost_enigma666@hotmail.com       thanks alot

Samer Salma
User offline. Last seen 4 years 1 week ago. Offline
Joined: 19 Jan 2011
Posts: 28
Groups: GPC Qatar

Hi Arnold,

Please send it to me also

My email is: saas70@gmail.com

 

Thanks

Samer

Saule Kokeyeva
User offline. Last seen 10 years 26 weeks ago. Offline
Joined: 10 Jan 2011
Posts: 3
Groups: None

Arnold,

 

Please send those details to me saule_kokeyeva@mail.ru

 

Regards,

 

Saule

Leoncio III Asilom
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 26 May 2009
Posts: 7

Hi Arnold

 

Can you post your steps in this forum so that everybody can see 

cuz the forum is full of email request 

 

 

Thanks

 

Leo

emee del mundo
User offline. Last seen 13 years 7 weeks ago. Offline
Joined: 28 Feb 2011
Posts: 3

Hi Mark,

Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...

Thanks.

Emee

emee del mundo
User offline. Last seen 13 years 7 weeks ago. Offline
Joined: 28 Feb 2011
Posts: 3

Hi Mark,

Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...

Thanks.

Emee

dindima manjunatha
User offline. Last seen 13 years 8 weeks ago. Offline
Joined: 23 Feb 2011
Posts: 2
Groups: None

Hi Arnold,

Please, also send me the steps on how to create the comulative late curve in P6.
This is my email :dindima83@gmail.com

Thanks & Regards

Dindima.

Eddy San Gabriel
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 9 Feb 2011
Posts: 20

this is a bit late for a request, please also send me this exercise.. thanks

Alaa Al haj
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

i Appreciate if anyone send copy to me

aalhaj@ccc.ae

Alaa Al haj
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

i Appreciate if anyone send copy to me

aalhaj@ccc.ae

Bert Ella
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 16 Feb 2011
Posts: 21

i agree to the suggestion of Mr. Waheed Mirza.

just try it. it's easy.

 

more power Planners!

Kannan Jaishankar
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 1 Jun 2004
Posts: 4

Hi Arnold & Others,

 

Can you please Send me the steps to be followed to create S- Curves for Both Early and Late dates.

My e-mail id is kannan_Jaishankar@yahoo.co.in.

 

Thanks in advance

DM Rabello
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 13 Feb 2011
Posts: 3
Groups: None

Olá Arnold

can you send me also 

enex@terra.com.br

Thanks

 

Rabello from Brazil

DM Rabello
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 13 Feb 2011
Posts: 3
Groups: None

Olá Arnold

can you send me also 

enex@terra.com.br

Thanks

 

Rabello from Brazil

Jorge Taguinod
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139

I did one just a couple of months ago.  Note that your schedule should not have any updates yet.  Then follow Karim Maghob's recommendation.  It shoudn't be rocket science.

Jorge Taguinod
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139

I did one just a couple of months ago.  Note that your schedule should not have any updates yet.  Then follow Karim Maghob's recommendation.  It shoudn't be rocket science.

Irfan Khan
User offline. Last seen 10 weeks 4 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi,

 

Pls send me copy here : irfan_kn2006@hotmail.com

 

thanks

Ayman Eleish
User offline. Last seen 12 years 4 weeks ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Hi Arnold,

Please, also send me the steps on how to create the comulative late curve in P6.
This is my e-mail..ayman_eleish@hotmail.com

waheed mirza
User offline. Last seen 12 years 2 days ago. Offline
Joined: 24 Nov 2010
Posts: 10

Hi .you can produce "s" curve in p6 only when you had assign budgeted value to activities.if you have then.go to "report "left side toolbar click on reports go to Reports group-Cost then Report group tabular then right click on monthly project cash flow.click run -report select ASCII text file then click ok.excel file will open showing cashflow.monthly and cummulative -month wise.now u are ready with data to produce s curve using excel chart.

Muhammad Aqeel
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 18 Apr 2009
Posts: 30
Groups: None
Hi Arnold,

Can u send me also the procedure to my email ad:

maqeel2008@hotmail.com   Thanks & Kind regards,
Y Malik
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 27 Nov 2010
Posts: 5
Groups: None

Hi Arnold,

Can you please send me the steps at younus@ualberta.ca

Thanks,

Malik

Pat Smith
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 8 Apr 2009
Posts: 5

Arnold,

Please forward steps: rcktfanatic34@yahoo.com

Thanks!!

Cesar Zacarias Vi...
User offline. Last seen 4 years 29 weeks ago. Offline
Joined: 27 Sep 2007
Posts: 6

Hai,

 

Arnold, can you post me also the steps on below mail:

cesar_zacarias@orascomci.com

Thanks very much.

 

Cesar

walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

 

Good morning arnold,

Could you send me the file ?     walid_lahiani@hotmail.fr

 

Thank you

Anthony Delmiguez
User offline. Last seen 6 years 9 weeks ago. Offline
Hi Arnold! Can you share the steps also? My e-mail address is LSSAPD@YAHOO.COM I'm a new member. Best regards!
Ramzi AGOUDJIL
User offline. Last seen 8 years 9 hours ago. Offline
Joined: 19 Sep 2010
Posts: 5
Groups: None

Dear Arnold,

Please send me:

agoudjilramzi@gmail.com

Thnx.

Ramzi

Mark Porter
User offline. Last seen 10 weeks 4 days ago. Offline
Joined: 8 Aug 2007
Posts: 55
Groups: None
Hi Arnold,

Way back at post # 2 you stated that you must create two baselines & attach to the project, these baselines are as follows;

1. Baseline (Early Planned) - Project Baseline
2. Late Planned - Users Primary Baseline (BL1)

I was kindly wondering how you are creating your late baseline?

Currently, I run a Global Change to match the start / finish dates to the late dates, but the only other way that I can think of getting the late dates is by assigning "As late as possible" constraints & scheduling accordingly...

Do you know of any settings that allows you to schedule the program based on the late dates, or do you know of a easier way that I may not know of?

Kind Regards

Mark Porter
Mina Arsal
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 15 Sep 2008
Posts: 15
Groups: None
Hi Arnold,

Can u send me the procedure to my email:

mina.arsal@gmail.com

Thanks in advance.
abbas india
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Hi Arnold,

Can u send me also the procedure to my email ad:

saidumd@gmail.com

Thanks.
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Guys,

Already sent.

Jun Partoriza
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 11 Sep 2009
Posts: 5
Can u send me also the procedure to my email ad:
jford_dmx@yahoo.com.

Thanks.
pat Gatus
User offline. Last seen 14 years 31 weeks ago. Offline
Joined: 11 Sep 2009
Posts: 11


Hi Arnold,

i am just a beginner in P6 and i would very much appreciate if you please send me the steps also

thanks & regards,

Pat

My email add is uangbo08@yahoo.com
Willem Viljoen
User offline. Last seen 14 years 30 weeks ago. Offline
Joined: 9 Sep 2009
Posts: 3
Groups: None
Hi Arnold,

Would you mind sending me the steps as well.

wviljoen@ananzi.co.za

Thank you.

Willem.
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Guys,

Already sent.

tandyo winarno
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 14 Jul 2009
Posts: 25
Hi Arnold,

I also late for joining this topic. Would you please send the step to me to my email as follows:

tandyow@yahoo.com


Thanks and regards,
Tandyo
Roldan Bartolome
User offline. Last seen 4 years 27 weeks ago. Offline
Joined: 4 Aug 2007
Posts: 14
Arnold,

can you send also to my e-mail add; rgbart2@yahoo.com

Thanks & regards


mujaffer shaikh
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 8 Sep 2009
Posts: 4
Sir Arnold ,
Can you please forward me at ( mujaffer.shaikh@gmail.com ) as well the steps for generating cumulative late curve.

Thanks & regards

Mujaffer
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Guys,

Already sent.

Francis Moyalan, ...
User offline. Last seen 4 years 49 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
Hi Arnold,

I am late comer to this forum, if you don’t mind please send me the details to my e mail id-

francis34@rediffmail.com

Cheers

Francis M Varghese
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Guys,

Already sent.

wungyea lee
User offline. Last seen 14 years 19 weeks ago. Offline
Joined: 23 Dec 2005
Posts: 14
Hi! Arnold,
In digging past forum posts I have found this topic, would you mind e-mail me the step by step guide in create the said ?
my e-mail is wungyea@mail.nsysu.edu.tw
thank you in advance!





Lee Wungyea
Ghassan Zihri
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 13 May 2006
Posts: 10
Groups: None
Hi Arnold,

can you send me the same to gzihri@yahoo.com?

thanks & regards,
ghassan
forat faris
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 28
Groups: None
Hi

can you send it also to foratfaris@maktoob.com

Thanx in advance!
forat
abbas india
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Dear Arnold,

Please send me as well.

thiru_abbas@yahoo.com

Many thanks
Abbas.
Scarllet Pimpernel
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 19 Jul 2009
Posts: 152
Dear Arnold,

Please send me:

ellenedar@yahoo.com

Many thanks
Scarllet
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Guys,

Already sent.

osama Eltantawy
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 25 Jan 2009
Posts: 12
Groups: None
Dear Arnold,

Could you please send me the steps.

E-Mail:usama022007@yahoo.com

Thank you for your help.
Osama
Manish Kumar Pandey
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 10 Sep 2006
Posts: 6
Groups: None
Hi Arnold or other folks,

Please send me as well. I still don’t understand how to generate s-vurve in P6

my email id: manish_k_pandey@yahoo.com

Thanks in advance

regards

Manish
Manish Kumar Pandey
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 10 Sep 2006
Posts: 6
Groups: None
Hi Arnold or other folks,

Please send me as well. I still don’t understand how to generate s-vurve in P6
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Guys,

Already sent.

Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Arnold,

Kindly spare me a copy please? You may send it to esariete@yahoo.com

Thanks and regards
Willem Prinsloo
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 33
Groups: None
Hi,

Can you please sent them to me. willemp@adpmetco.co.za

Thanks
Willem
Ronald Romero
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 13 Nov 2006
Posts: 63
Sir,

Kindly send me also the steps in creating S curves in P6 at ronnieksa@yahoo.com .

regards,

Ronnie
HARRED CECE
User offline. Last seen 11 years 47 weeks ago. Offline
Joined: 12 Jan 2009
Posts: 5
Groups: None
Hi Arnold,

Please send me a copy of the methods.

Best regards,

harredcece@yahoo.com
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Devrim,

Already sent

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi KZ,

Thank you very much for the pleasure. I am dedicated and glad to help.

Thanks gain.

Regards,

Arnold