In P6 can you copy resources from activity to activity?

Member for

18 years 9 months

Neil

Maybe it’s not the way you intended.

View "Activities" --> On the right side of the Primavera Window you find the icon "Assign Resources". --> select the activities where you want to replace a resource (by filter or just manually) --> select the resource to be replaced --> Click onto the icon "replace" (just above the help-icon) --> select the resource to be assigned to those activities.

This window can remain open while you run different filters, sort or select different activities.

Regards

Dieter

Member for

18 years 6 months

Hi Neil,



Yes you can.. Including Resources.



1. Open the two projects you wanted to cut & paste activity.

2. In P6 Activity Window, select the activity & right click select Cut.

3. Paste the cut activity into another project in the same activity window.



However, If you cut these activities & paste it to another project then you will loss these activities from its original project. To avoid this, make a backup copy of the original project.



HTH.



Arnold

Member for

18 years 6 months



What do you mean, copy resources from activity to activity?

You can copy the resources assigned to each activity if you will copy/paste the activities by checking all the boxes in Copy Activity option.