Importing Activity Data from xls

2 replies [Last post]
Philip Richards
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 29
Groups: None
I am trying to import new activiies to an existing P5 programme, from an xls speadsheet.

Activity ID, Name & Primary constraint (Fin on or After) import ok. I cannot however get the activity type (Fin Milestone) or the date to carry over. I am exporting first to create a template, and retaining the formats etc. It is difficult to format the date, but even if I copy an exact date from the export, and re import, P5 does not seem to recognise it.

Any suggestions please?

Replies

Philip Richards
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 29
Groups: None
Rodel

Thanks, but I have followed your advice, and still no joy.

I have managed a workaround, by importing the xls to P3, then converting the P3 programme to P5.

Regards
Phil
Rodel Marasigan
User offline. Last seen 12 hours 9 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Philip,

If you export the template it should be okay. Date format is in text but it also accept any date format in excel. If you are importing finish milestone activity you should input only the Early Finish date. If start milestone activity then only Early Start.

Import Structure:
Activity ID
Activity Status
WBS Code

These three fields is a must and should enter the data. If you are not familiar on these function, I suggest that before exporting your template, enter a sample data of each activity type that you want to import so you will have an idea of what kind of format when you enter the data into your template. If you include duration it overide your date and use the project calendar.

Regards,
Rodel