Progress Curve

6 replies [Last post]
Emmanuel Udo
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 10 Feb 2004
Posts: 14
Hi,
I need to modify the vertical axes of the progress curve.
The curve was developed using expense values. But I need to remove the $ signs and possible replace it with %. Is this possible? has somebody done it before?
Please, advise.


Emmanuel

Replies

sachin sangai
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 8 Oct 2005
Posts: 12
hi guys
Thanks for the help. but can I keep different scales for the histogram and the curve and can i show the values (Data labels) as we can in excel.

sach
Henk van der Heide
User offline. Last seen 6 years 20 weeks ago. Offline
Joined: 7 Aug 2004
Posts: 101
Dinesh,

Yes you’re right i misunderstood
You have to divide by your total budget and multiply by hundred (or as you say divide by total budget/100) works very fine.

Thanks

regards

Henk
Dinesh Kumar Dama...
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Henk,

I tried it and it works.Let’s say you have a planned value of 37000000, you devide it by 370000 and include % sign in the unit of measure.The planned value will be shown as 100% and actuals and earned value will be calculated and shown accordingly.Try it.

Thanks & regards

Dinesh
Henk van der Heide
User offline. Last seen 6 years 20 weeks ago. Offline
Joined: 7 Aug 2004
Posts: 101
Hi Dinesh,

I dont think this is the same.
The meaning is to see the % of the total budget (total budget is 100%). to do this you have to divide through the total budget. Not a number like 10/100 or 1000.

Regards

Henk

Dinesh Kumar Dama...
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi,

May be you can try to use the following :

Under activity profile/resource profile, choose profile options >graph tab > tick calculate average >devide the total shown on the profile by 10 if it is in 1000 and 100 if it is in 10000 and so on >type % in the units of measure> apply.

Thanks & regards

Dinesh
Henk van der Heide
User offline. Last seen 6 years 20 weeks ago. Offline
Joined: 7 Aug 2004
Posts: 101
Hi,

It’s not possible to set % on one of the Axis.

You better make a timedistributed report, dump it to excel.
The new release will have this option (so i’m told).

Regards

Henk