SureTrak - data date line does not fall directly below

1 reply [Last post]
Ashish Abraham
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 28 Nov 2006
Posts: 16
Groups: None
Hi everyone,

I have a question in Primavera SureTrak. I have a SureTrak schedule, and I notice that the Data Date line does not fall directly under Week 1 (ordinal dates). It is located about a day or two later. Is there a way to fix this so that the Data Date line fall directly at the start of Week 1?

Thanks!

Replies

Rafael Davila
User offline. Last seen 14 hours 43 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Change your Data Date and or Project Start Date to be on Sunday as ordinal dates count start on the first day of the calendars week, ie. on Sunday.