Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems?

1 reply [Last post]
John Reeves
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 10 May 2013
Posts: 342
Groups: None

Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems? - These items are intertwined - one of the worst things you can do is make the schedule into either a submittal log (or a to do list).  But how to you efficiently feed the info between them - surely P6 has addressed this.  I think years ago they did with their Old CM tools (ie Expedition - yes I am old.) but by getting fancier I think that easy link was lost.  I only see them excel now days.

Replies

Zoltan Palffy
User offline. Last seen 3 days 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the old expedition is not Primivera Contract Manager and you can inport of there into excel.

The other option is to build a submittal log yourself by using the p6 import spreadsheet