Exactly, but still some people insist you manage with a plan that includes the assumption for some rain at specific dates or range of dates. This is basic project risk management.
The calendar method shall be applied to determine extension of time but not for managing the schedule. What if you plan for some rain and assume it will be tomorrow but it does not rains, the schedule will misled people into not working tomorrow.
Critical Chain promotes the use of separate activities as buffers to avoid padding, which is an improvement, but is flawed with regard to feeding buffers because as soon as the critical chain changes they might no longer be feeding into the critical chain and if not enough new feeding chains will happen.
A better approach is favored by Spider Team, it does not depend on padding, it does not use activities to represent buffer, no special software is needed to apply the concept.
A weather contingency is best placed on the callendar allocated to outdoor trades. Anticipated weather can then be substituted for real weather in the weekly update.
Member for
21 years 7 monthsIt is wrong to manage a
It is wrong to manage a schedule under the assumption it will rain tomorrow and therefore there will be no scheduled work for tomorrow.
Both shall be transparent, otherwise those in direct management of the means and methods will have no other option than to recur to a Ghost Schedule.
http://www.stevencevans.com/float/
http://www.fplotnick.com/constructioncpm/2016Presentations/MON37-PPR.pdf
Member for
19 years 10 monthsHi RafaelMost peopeprefer to
Hi Rafael
Most peopeprefer to do it properly.
Best regards
Mike Testro
Member for
21 years 7 monthsExactly, but still some
Exactly, but still some people insist you manage with a plan that includes the assumption for some rain at specific dates or range of dates. This is basic project risk management.
Member for
19 years 10 monthsHi RafaelYou only stop work
Hi Rafael
You only stop work when the weather is bad - not when you have a wet day forecast on the programme.
Best regards
Mike Testro
Member for
21 years 7 monthsI do not like strategies that
I do not like strategies that promote lies and deception, schedules shall be transparent and not a bunch of lies.
Member for
21 years 7 monthsMike,The calendar method
Mike,
The calendar method shall be applied to determine extension of time but not for managing the schedule. What if you plan for some rain and assume it will be tomorrow but it does not rains, the schedule will misled people into not working tomorrow.
Critical Chain promotes the use of separate activities as buffers to avoid padding, which is an improvement, but is flawed with regard to feeding buffers because as soon as the critical chain changes they might no longer be feeding into the critical chain and if not enough new feeding chains will happen.
https://wafimohtaseb.com/2012/05/27/project-scheduling-best-practices/
A better approach is favored by Spider Team, it does not depend on padding, it does not use activities to represent buffer, no special software is needed to apply the concept.
http://www.spiderproject.com/images/img/pdf/Success%20Driven%20Project%20Management%20Paper.pdf
Best Regards,
Rafael
Member for
19 years 10 monthsHi Dr Paul.A weather
Hi Dr Paul.
A weather contingency is best placed on the callendar allocated to outdoor trades. Anticipated weather can then be substituted for real weather in the weekly update.
Simple realy.
Best regards
Mike testro