Financial Periods in p6

No replies
Amro Ahmed
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107

I'm updating one project by financial periods in p6 .showing total  actual units for one of activities  not correct and not matching with actual cost (which is right) although  all indvidual periods' units and cost are right.