Modifications in the updated Program from Base plan
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hi Shaji
In the existing baseline [ without updates ],you can revise the network logic where you find the issues and than update it with actual site scenario and check the status.
Dear Shaji,
Of course it is the right thing to do. It depends on the size of your project and the complexity of it. If you have a Contract and you submitted a Program of Works and the Engineer didnt return with comments, then this is the Schedule that you (Contractor) will be following to complete the project.
I assume that you are using FIDIC, and following article (8/3) once you realize that the actual progress at site does not represent the Program of Works, you need to modify your Program of Works to represent the actual (new information), making sure that you abide by the Conditions of Contract (scope, time).
With kind regards,
Samer