whats the meaning of CTR???

8 replies [Last post]
Rolando Rivera
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 12 Sep 2006
Posts: 5


I don’t know where to place this general question, but as stated above, what "CTR" stands for?

The client asked for a "CTR schedule" but nobody knows what CTR stands for?


needs someones help....thanks.

Replies

Rolando Rivera
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 12 Sep 2006
Posts: 5
thanks to your reply guys....


Cost, Time & Resources is the meaning of the CTR i am looking for.



cheers,


rolando
Osama Warid
User offline. Last seen 9 years 30 weeks ago. Offline
Joined: 5 Mar 2007
Posts: 40
Groups: None
Nice information
Xifan Xie
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 17 Oct 2004
Posts: 16
It means Cost, time and resource, it’s implemented by Worleyparons
Basir Ahmed
User offline. Last seen 14 years 25 weeks ago. Offline
Joined: 24 Feb 2009
Posts: 14
If i am not wrong CTR stands for ’Cost Time & Resource’.

In simple words it is a BOQ with price for each item included. and a tentative schedule is also submitted with it. only Level 1 activities.

so a CTR based schedule means that the schedule should contain all the activities that cover the line tiems present in the CTR.

I hope i have answered your question.

Cheers.

Basir
Basir Ahmed
User offline. Last seen 14 years 25 weeks ago. Offline
Joined: 24 Feb 2009
Posts: 14
If i am not wrong CTR stands for ’Cost Time & Resource’.

In simple words it is a BOQ with price for each item included. and a tentative schedule is also submitted with it. only Level 1 activities.

so a CTR based schedule means that the schedule should contain all the activities that cover the line tiems present in the CTR.

I hope i have answered your question.

Cheers.

Basir
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Look to Wideman Comparative Glossary of Project Management Terms at http://maxwideman.com/pmglossary/ for answers to these types of questions. Good luck!
Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline
CTR stands for Cost, Time, Resource

They tend to be synonymous with workpacks

Cheers,

G
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Rolando,

Can you please give us an idea about what you are working on. It might be an abbreviation of the Project you are working on not a type of schedule that your manager asked you to do.

C might be: Critical, Crashed, Compressed
R: Recovery

With kind regards,

Samer