Critical Path and Schedule Constraints
Forum Sponsor
Top Posters
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
Samer
Of course you need to represent your Contractual requirements, no question about it. Constraints hide logic, my point is that you can show Contractual requirement somewhere else. Use of baselines to me is not enough you should be able to see some parameters that tell you where you are in relation to your constraints but without hiding logic. Constraints make float somewhat useless.
At times even when working with my own schedules the contractual constraints do not let me see the logic, especially after updating when you get different values of negative float. It is an issue that has been discussed before with regard to float. I did created a new pasting as to keep focus on my concern with regard to constraints, the cause not the symptoms, perhaps this is the key.
Critical Path and Negative Float
Total Float
Critics Can’t Find the Logic in Many of Today’s CPM Schedules
Managing Multiple Milestones
Longest Path Value (to the Rescue)
Making CPM More Transparent
Best regards,
Rafael
Dear Rafael,
You need to represent your Contractual requirements. If you have a mall and you want to open up before Christmas, then you need to hand over the works before the 1st of December or you will miss the buying power of the season and all your customers will default on their contracts.
On the other hand, the majority of the Contracts do not have a MUST FINISH by date.
With kind regards,
Samer