LNG Terminal (onshore/offshore) EPC Schedule !
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I was assigned to planning a new schedule for LNG ( EPC)
I want to learn more from all of you experienced in this field.
many thanks!
Hi Surai
I worked on the civils section of the LNG terminal at Milford Haven and it was the most technically complex sequence of work I have ever encountered.
I couldnt build it so I did not try to plan it.
Samer is right - dont try to plan it yourself - go to the engineers and then schedule their plan for them.
Best regards
Mike Testro
Dear Surai,
The typical processes for each project are:
1. Engineering
a. Material Submittals
b. Shop Drawings
2. Procurement
a. Long Lead Items
b. Standard items
3. Construction
4. Handing Over, Testing and Commissioning.
For an LNG project, the major steps are:
1. Drilling offshore
2. Storing the Gas offshore
3. Transforming the Gas into Liquid
4. Transporting the Gas to onshore
5. Storing the Gas onshore
6. Processing the Gas
7. Trasporting the Gas to destination
You need to create buildings, piping and piperacks along the way. Constructing these out of concrete and steel structure would be according to the specification, drawings and BOQ that you have. The more indepth information that is required about completing the plants, would be secured from special process engineers. Your best source of information is you team members and Project Managers.
With kind regards,
Samer