Assigning Non labor resources inquiry

1 reply [Last post]
George Ridulme
User offline. Last seen 12 years 5 days ago. Offline
Joined: 16 Jun 2008
Posts: 21
Hi guyz,

I am having difficulty in terms of assigning non labor resources.
The problem is when I assign a nonlabor, let say a crane at 10hrs/day (budgeted units/time)on the resources for a certain activity, once i opened the resourced usage profile, it doesnt reflect a 10hrs/day, (usually it reflects more than what i have assigned on the resource). Thus, if i have only 10hrs working time/day, the crane reflects an overallocation.

Do i miss something here,


Thanks in advance,

George

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi George,

Before assigning the Nonlabor Resources, try to change the Default Units/Time equals to 10/d then assign it to corresponding activities.

Try to use "Fixed Duration and Units/Time" as Duration Type. The only thing is, your Budgeted Units will change.

HTH.

Arnold