unsatisfied constraints

3 replies [Last post]
Mohammed Abo El Magd
User offline. Last seen 14 years 35 weeks ago. Offline
Joined: 29 Nov 2004
Posts: 46
Groups: None
Dears,
Have anybody find a definition for this terminology,, (( Unsatisfied Constraints)) appears when viewing schedule log in P6 ?

Please advice.

Replies

Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mohammed,

You’re welcome. No, I didn’t find it in HELP. I read in one of many articles as well as, it so happen that it’s part of my experienced and I tried to experiment using all types of constraints.

Thanks.

Arnold
Mohammed Abo El Magd
User offline. Last seen 14 years 35 weeks ago. Offline
Joined: 29 Nov 2004
Posts: 46
Groups: None
Hi Arnold,
This is very good. Thanks. Have you find it in the help ??

Regards
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mohammed,

Unsatisfied Constraint occur only if your activity has a constraint assigned "Start on", "Start on or Before" & "Mandatory Start" later than the assigned date.

Say for example:
You assigned constraint to your activity that starts on 04-Dec-08 however, your actual start is on 06-Dec-08. This is the unsatisfied constraint.

HTH.

Regards,

Arnold