Export from P6 TO P5

2 replies [Last post]
Mallesha Chandra ...
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 21
Pls. explain how to export p6 schedule or resource loaded schedule to p5.

Regards

Mallesha.c

Replies

Mallesha Chandra ...
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 21
Thanks Arnold

Regards

Mallesha.c
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mallesha,

Follow the following steps:

1. Open the project you wanted to export.
2. Go to File Menu --> Export
3. In Export Format, Select Primavera Contractor 5.0 - (XER) then NEXT
4. Export Type --> Project then NEXT
5. Project to Export --> NEXT
6. In File Name, select the location where to SAVE your .xer file
7. Select Finish when done.

Other way around is by opening using Notepad.

Follow all the Steps above except step #3 instead select Primavera PM/MM - (XER)

After finishing the export. Go to the .xer file, select & right click & open with NOTEPAD. Change 6.0.0 to 5.0.0 and then SAVE.

HTH.

Arnold