MS-Project

2 replies [Last post]
rajesh anand
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 5 Dec 2006
Posts: 27
Hello to all Planners

I have a doubt when I insert resources to the activities, why does the duration changes. Please clarify it.

regards

rajesh

Replies

Tommy Nug
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
You can also go to Tool/Option, and disable effort driven option to change the property every time you create a new activity.
J Venkatesh PMP P...
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
when u r entering resource , try by disabling Effort driven option, and also t depends upon the type u r choosing either Fixed time / Fixed units ....

Venkat