Heat Tracing Norms.

3 replies [Last post]
DATTATREYA PADHARTHI
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
Friends,
One part of our project includes preparating of small work requests & estimating the Man-hours required to complete the Engineering work.
Electrical Heat Tracing expert seldom gives the Man-hours saying that it cannot be quantified at the start & even when Isometrics are issued.. My contention is that at some point of time, with historical data etc, one can always estimate the Man-hours required with more or less accuracy.
Are ther some standards linking Piping Isometrics (Length/Volume, type etc) with the Tracing Quantities & with Tracing efforts.
Cheers

Dattatreya

Replies

Izam Zakaria
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Of course ..then I propose to create a new norms...dun too much depends on what their have...planners must creative...
DATTATREYA PADHARTHI
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
Dear Izam,

You got me wrong. I am not talking about the relationship between deliverables.
My query was even after giving ISO’s for the Tracing team, we do not get how many mhrs/time is required for tracing work let alone getting a decent estimate after Layout/design.
This affects completion dates.
Normally when doing an EPCM/LSTK from the start we do have norms, but when the Project reaches a stage where Offshore Works come in piecemeals it becomes difficult to estimate.

Cheers

Dattatreya
Izam Zakaria
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Colleague,

To assign manhours for each deliverables nor CTR (Cost Time Resources based on nos of drawings, philosophy, specification and reports. if u talking bout link, of course Piping isometric will implemented after PDMS model and P&ID firmed out.