Where the professionals network; have you Self Assessed? become a Guild Reviewer? or reviewed Guild Phase 2?

How to get planned % weight from P3.1?

8 replies [Last post]
Joseph Erwin Carg...
User offline. Last seen 1 week 1 day ago. Offline
Good day guys,

does anyone know how i can determine the Planned % weight for the whole project? so that i can plot it on S-Curve using Excel.

thanks

Replies

Lotfi Ghodhbani
User offline. Last seen 50 weeks 5 days ago. Offline
Joined: 11 Jun 2004
Content Credits: 4
Joseph,

The process to get planned % weight and eventually the actual one is very long and complex but it gives very good results :

1 ) Declare a resource (weight);

2 ) Assign the weight of each tash of the schedule;

3 ) Declare resource variables under Custom Data Items;

4 ) Run Report Writer to generate Level 1/2/3 Progress Reports. This requires a good understanding of P3 macro-programming under Report Writer ;

5 ) Generate reports in CSV Format to allow use with Excel;

6 ) Update your "S" Curve in Excel Format.

Regards,

Lotfi
Joseph Erwin Carg...
User offline. Last seen 1 week 1 day ago. Offline
Rollen,

tnx for that, it surely helps..

tnx guys
Svein Myklebust
User offline. Last seen 3 years 29 weeks ago. Offline
Joined: 27 May 2006
Content Credits: 25
Why Excel?
Just because it’s a program they know
or are they gonna use it for something?

Svein
Rollen Lopez
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 12 Nov 2005
Content Credits: 17
Hi Joseph,

Here is one way you can transfer your curve, graphics to excel or word.

In primavera look, where your curve, graphics are being displayed. Choose menu option - Edit, Select all,or simply control A.

Now, switch to your excel file choose menu option, edit,paste special, (make sure you do not paste this time),select picture(enhanced metafile). Then you will see your graphics in the same way as what you see in Primavera Look. You may resize according to your preference.

Hope this helps,

Cheers,

Rollen
Joseph Erwin Carg...
User offline. Last seen 1 week 1 day ago. Offline
Thank you james...

joseph
James Bridges
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 10 Nov 2004
Content Credits: 18
Groups: Building Works

Joseph,

I’m sure there is a way to export the curve to excel, I think it’s been discussed else where on these forums. As a last resort to could always transfer the curve into excel manually.

You can show planned percentage complete based on duration. You should be able to select planned percentage complete as one of the columns to display, if I remember correctly.

Regards
Joseph Erwin Carg...
User offline. Last seen 1 week 1 day ago. Offline
James

Good day,i already generated a curve...but our client want it to be ploted on excel format...is there any way that a curve generated from p3 can be transfered to excel?

and if there will be no resources is it possible for p3 to give the planned percent weight each week?

tnx,

joseph
James Bridges
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 10 Nov 2004
Content Credits: 18
Groups: Building Works
You need to add a resource or cost to each activity before you can generate a curve.