Change in Budgeted Units

3 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 6 days 7 hours ago. Offline

Hello Everyone,

 

I exported a schedule, rerouce loaded it and imported it back to the P6.

 

After checking some activity I saw that I for got to add some other resource for the same activity. But when I add this resource through Primavera it changes the existing allocated reource. I do not want that to happen. Please advice me on how to tackle it.

 

Example :

Activity A had a resource at First: Carpenter - 20 Hrs .

 

I missed adding Labor, so when I added it. It distributes the 20 Hrs, Now Carpenter = 10 Hrs, Labor = 10 Hrs

 

Thanks

Jithin

Replies

Rodel Marasigan
User offline. Last seen 23 hours 31 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699

You're welcome, happy to help.

Jithin Kambhikanam
User offline. Last seen 6 days 7 hours ago. Offline

Thanks Rodel,

 

A good info.

Rodel Marasigan
User offline. Last seen 23 hours 31 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Jithin,

You need to change the Resource assignment calculation when adding or removing resources. On menu select Edit--> User Preferences. When the pop-up window User Preferences click Calculation tab and select Preserve Units, Duration, .... see below:
Resource-Assignment-Option