"Necking" Bars on Gantt Chart - MSP2007

Member for

22 years 11 months

Hi Evgeny,

Thanks for the reply. Unfortunately it is not the non-working calendar dates I want to show, as this would effectively "block out" the non-working time of all tasks rather than just those with a certain calendar.

Regards,

Tony

Member for

17 years 9 months

Tony,

I only know a way how to show non-working time of a specific calendar. But it will show it for entire Gantt chart in a background. So this approach would not work if you want to show different tasks with different calendars.

You need to right click on the Gantt Chart and then go to Nonworking time.

http://office.microsoft.com/en-gb/project-help/change-the-appearance-of-nonworking-time-HP045303811.aspx

Regards.

Evgeny