updating hammock task in MSP 2007

3 replies [Last post]
kp rao
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 29 Jul 2011
Posts: 18

Dear planners,

I am using MSP 2007.Hammock activity is not updating itself.How to set auto update of hammock task.It is like update the tasks and hammock task will be updated.

urgent help

Regards,

kp

Replies

Niek Zonneveld
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None

kp,

You can do this but it is not straightforward.

You can copy a cell in MSP and then paste the content as a link into another cell (through paste special, paste link)

Just copying a date into the destination cell won't work because that will normally just impose a constraint and not change the duration.

Cleaver use of formula's in combination with the above links will probably get you there, but remember MSP gets 'nervous' from these links as it keeps recalculating/updating continuously.

H.T.H.

kp rao
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 29 Jul 2011
Posts: 18
Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

Edit, Links, Update