Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2004-07-31 05:13 Permalink RE: Page breaks in reports There is no pagebreak functionality in MSP reports, whatever MSP version you are using. Try replacing a report by the equivalent View, for instance "Task list" view instead of the "Task" report, ... Use Insert, Pagebreak to break between two rows. Alexandre Member for 22 years 7 months Member for 22 years 7 months Submitted by Dayanidhi Dhandapany on Thu, 2004-07-29 11:00 Permalink RE: Page breaks in reports I believe there is no such facility available in MS Project 2000, either you have to insert page break manually in task sheet view or write some customised programme in VBA / Macro for MS Project. Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2004-07-31 05:13 Permalink RE: Page breaks in reports There is no pagebreak functionality in MSP reports, whatever MSP version you are using. Try replacing a report by the equivalent View, for instance "Task list" view instead of the "Task" report, ... Use Insert, Pagebreak to break between two rows. Alexandre
Member for 22 years 7 months Member for 22 years 7 months Submitted by Dayanidhi Dhandapany on Thu, 2004-07-29 11:00 Permalink RE: Page breaks in reports I believe there is no such facility available in MS Project 2000, either you have to insert page break manually in task sheet view or write some customised programme in VBA / Macro for MS Project.
Member for
22 years 9 monthsRE: Page breaks in reports
There is no pagebreak functionality in MSP reports, whatever MSP version you are using.
Try replacing a report by the equivalent View, for instance "Task list" view instead of the "Task" report, ...
Use Insert, Pagebreak to break between two rows.
Alexandre
Member for
22 years 7 monthsRE: Page breaks in reports
I believe there is no such facility available in MS Project 2000, either you have to insert page break manually in task sheet view or write some customised programme in VBA / Macro for MS Project.