Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Front loaded & Back Loaded Resource Curve

2 replies [Last post]
Mohammad Mojahid ...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 19 Jan 2008
Posts: 18
Groups: None

Dear PP Friends

I need your feedback in regards the following question

  1. What is the definition of Front loaded & Back Loaded Resource Curve.
  2. which resource curve will give correct progress status.
  3. To get the resource curve I have to load from global Resource curve to each resources.
  4. The last how I will get S-curve,  

for that I shall be very thankfull to all of you

Replies

Mohammad Mojahid ...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 19 Jan 2008
Posts: 18
Groups: None

Dear You reply me or you asked quetion

planning engineer
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 20 Oct 2011
Posts: -1

 

Q1wysiwyg_imageupload::height=422,width=291

I DID'T GIVE ANY DURATION SO HOW PRIMAVERA ASSING THE DURATION?

Q2

DIFFERENCE BETWEEN START & FINISH IS 4 WHILE IT SHOWING DURATION 9

Q3

ALSO HOW IT CALCULATE THE TOTAL FLOAT

Q4

IS MY ASSINGING OF RELATION BETWEEN THE ACTIVITY IS CORRECT OR WRONG

Q5

WHAT IS THE BEST WAY TO ASSING RELATION SHIP BETWEEN ACTIVITIES.

Q6

IF I WANT TO MAKE THE ACTIVITY A1112 CRITAICAL SO WHAT I DO FOR THAT PURPOSE?

Q7

WHAT IS EASIEST WAY TO DRAW THE CRITICAL PATH IN PRIMAVERA 6?

Q7

HOW THE STAR ASSOCIATED WITH DATES ARE REMOVED?