Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revised and Recovery Programs

13 replies [Last post]
Abdallah Abu Ghaz...
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 3 Dec 2009
Posts: 11
Groups: None
Hi;

What exactly is the difference between Revised and Recovery Programs.

Thanks

Replies

Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

It depends. You need to go back to the definition of a crashed schedule (increasing the resources) and check if you can use it to your advantage in the Schedule that you want.

With best regards,

Samer
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

In connection to forum topic does crashed schedule is a part of recovery or revised programme?
Abdallah Abu Ghaz...
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 3 Dec 2009
Posts: 11
Groups: None
Thank you all for the valuable replies
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Alright thanks for your support samer
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

You are correct. The reason the Engineer request a revised schedule is that the approved schedule at the start of the project does not represent the actual work ongoing at site. In most cases, you have a slow progress and the activities start and completion are late.

Therefore, in most cases, the revised schedule will indicate that the project will be completed at a later date.

With kind regards,

Samer
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Samer

In connection to previous message you have mentioned In revised schedule projection completion date is flexible, in the sense it could vary from consented schedule completion date ,am i correct ?
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many thanks samer
It is very clear from your message
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

What exactly is not clear for you. In the "Recovery" Schedule, you want to recover the lost time and maintain the end date. Crashing and Resource Leveling are planning tools to increase the productivity on the project.

Whereas, in the "Revised" schedule, you want to complete the project and the end date is flexible.

Best,

Samer
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
hi

I need a clarification please respond for the below message

Recovery schedule : Here we maintain same project completion date as in consented baseline but modification could be done to those activities which are yet to start or progressing by crashing and resource acceleration

Revised schedule : Here we slipped the consented project completion dated and we plan for activities which are yet to start or progressing


Anoon Iimos
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Abdallah,

Yes and No, as they might ask you to revise the schedule in order to recover.

You have to clear this out considering that when you run or calculate the schedule automatically, it will give you a result that might differ from what as planned. So in order to maintain the same timeframe (as in baseline), you need to do some modifications or revisions.

cheers
Abdallah Abu Ghaz...
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 3 Dec 2009
Posts: 11
Groups: None
Thank for the replies;

But what I want to clear out is that If I am asked for a revised schedule the finish date of the project will change and for the recovery it should be the same, right?
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Abdallah,

Recovery: You would rethink you schedule to come up with new methods to finish on time as much as possible.

Revised: You will revise the schedule so that the new schedule will reflect the actual progress of work at site.

With kind regards,

Samer
Anoon Iimos
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
For me, a recovery program means that you may do some modifications but the new program is still aimed on the same or original target, while a revised program may have some changes that affects the whole timeframe or the scope.