Schedule of application for subcontract
Forum Sponsor
Top Posters
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
Not quite sure what you are trying to explain so the only answer I can give is that if the provisions of the contract do not comply with the provisions of the HGCR Act with regard to payment, then the relevant provision of the Scheme for Construction Contracts replaces it.