Planned Start

I would like to know how to switch on Planned Start and Planned finish date when baselining the projects.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Hemant

Welcome to Planning Planet

If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.

If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.

You can also set a column to show the diference in days.

Hope that helps

Best regards

Mike Testro

H
Hemant Bharat 👤 Member for 15 years 7 months

What I meant was how to switch on the date columns with the "planned start" and "planned finish" dates. I have baselined the project already.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts