Formatting the weekend display

L
Laurie Willis 👤 Member for 19 years 7 months

Alexandre thanks for your reply. In the end the customer decided they like the bars, so I didn’t have a chance to try out your suggestion.



But thank you for your help.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Laurie,

I am using PP8; I would check Work Pattern in the Library: The saturdays and sundays your wp should be set-up as follows in the 8hr/day, 5d/w pattern:

Non-working: 00:00 - 09:00 (or 08:00)

Week-end: 08:00 (or 09:00) - 17:00

Non-working: 17:00 - 00:00

and as follows in the 8hr/day, 7d/w pattern:

Non-working: 00:00 - 09:00 (or 08:00)

Working: 08:00 (or 09:00) - 12:00

Non-working: 12:00 - 13:00

Working: 13:00 - 17:00

Non-working: 17:00 - 00:00

I presume the wrong display comes from there.

Hope this helps

Alexandre

Forum Sponsor

Top Posters

Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts